Direct Materials Variances Flashcards
1A favorable materials price variance coupled with an unfavorable materials usage
variance most likely results from
A. Machine efficiency problems.
B. Product mix production changes.
C. The purchase and use of higher-than-standard quality materials.
D. The purchase of lower than standard quality materials
Answer (D) is correct.
A favorable materials price variance is the result of paying less than the standard price for materials.
An unfavorable materials usage variance is the result of using an excessive quantity of materials. If a purchasing manager were to buy substandard materials to achieve a favorable price variance, an
unfavorable quantity variance could result from using an excessive amount of poor quality materials.
2A manufacturer planned to produce 5,000 units of its single product during November. The standard
specifications for one unit include ten pounds of materials at $.50 per pound. Actual production in November was
5,200 units. The accountant computed a favorable materials purchase price variance of $580 and an unfavorable
materials quantity variance of $320. Based on these variances, one could conclude that
A. More materials were purchased than were used.
B. More materials were used than were purchased.
C. The actual cost of materials was less than the standard cost.
D. The actual usage of materials was less than the standard allowed.
Answer (C) is correct.
A favorable price variance indicates that the materials were purchased at a price less than standard. The
unfavorable quantity variance indicates that the quantity of materials used for actual production
exceeded the standard quantity for the good units produced.
3Under a standard cost system, the materials efficiency variances are the responsibility of
A. Production and industrial engineering.
B. Purchasing and industrial engineering.
C. Purchasing and sales.
D. Sales and industrial engineering.
Answer (A) is correct.
The materials efficiency variance is the difference between actual and standard quantities used in
production, times the standard price. An unfavorable materials efficiency variance is usually caused by
wastage, shrinkage, or theft. Thus, it may be the responsibility of the production department because
excess usage would occur while the materials are in that department. In addition, industrial engineering
may play a role because it is responsible for design of the production process.
9A company planned to produce 3,000 units of its single product, Titactium, during November. The
standard specifications for one unit of Titactium include 6 pounds of materials at $.30 per pound. Actual production
in November was 3,100 units of Titactium. The accountant computed a favorable direct materials purchase price
variance of $380 and an unfavorable direct materials quantity variance of $120. Based on these variances, one could
conclude that
A. More materials were purchased than were used.
B. More materials were used than were purchased.
C. The actual cost of materials was less than the standard cost.
D. The actual usage of materials was less than the standard allowed.
Answer (C) is correct.
The direct materials purchase price variance may be isolated at the time of purchase or at the time of
transfer to production. It equals the actual quantity of materials purchased or transferred times the
difference between the standard and actual unit prices. Hence, a favorable direct materials purchase
price variance means that materials were purchased at a price less than the standard price
10A purchasing manager was able to acquire a large quantity of direct materials from a new supplier
at a discounted price. The inventory supervisor is concerned because the warehouse has become crowded and some
things had to be rearranged. The vice president of production is concerned about the quality of the discounted
materials. However, the Engineering Department tested the new materials and indicated that they are of acceptable
quality. At the end of the month, the corporation experienced a favorable direct materials usage variance, a favorable
direct labor usage variance, and a favorable direct materials price variance. The usage variances were solely the
result of a higher yield from the new material. The favorable direct materials price variance is considered the
responsibility of the
A. Purchasing manager.
B. Inventory supervisor.
C. Vice president of production.
D. Engineering manager.
Answer (A) is correct.
A direct materials price variance is the actual quantity used times the difference between the standard
and actual prices. It is normally considered the responsibility of the purchasing manager because no
one else has an opportunity to influence the price. In this case, the purchasing manager obtained the
discount that led to the favorable price variance.
11Price variances and efficiency variances can be key to the performance measurement within a
company. In evaluating the performance within a company, a materials efficiency variance can be caused by all of
the following except the
A. Performance of the workers using the material.
B. Actions of the purchasing department.
C. Design of the product.
D. Sales volume of the product.
Answer (D) is correct.
An unfavorable materials quantity or usage (efficiency) variance can be caused by a number of factors,
including waste, shrinkage, theft, poor performance by production workers, nonskilled workers, or the
purchase of below-standard-quality materials by the purchasing department. Changes in product design
can also affect the quantity of materials used. Sales volume of the product should not be a contributing
factor to a materials efficiency variance
13Which one of the following variances is most controllable by the production control supervisor?
A. Materials price variance.
B. Materials usage variance.
C. Variable overhead spending variance.
D. Fixed overhead budget variance.
Answer (B) is correct.
The production control supervisor has the most control over the materials usage variance. The
materials usage variance measures the excess amount of materials used over the amount specified in
the standards. The materials usage (or materials quantity) variance, when unfavorable, is often
attributable to waste, shrinkage, or theft in the production areas. The excess usage occurs under the
supervision of the production department.
16In a standard cost system, the investigation of an unfavorable materials usage variance should begin
with the
A. Production manager only.
B. Plant controller only.
C. Purchasing manager only.
D. Production manager or the purchasing manager.
Answer (D) is correct.
An unfavorable materials quantity variance is usually caused by waste, shrinkage, or theft.
Alternatively, an unfavorable variance could be attributable to the purchasing department’s not buying
the proper quality of materials in an attempt to achieve a favorable material price variance. Thus, either
the production manager or the purchasing manager could be responsible for a material usage variance.
17Under a standard cost system, the materials price variances are usually the responsibility of the
A. Production manager.
B. Cost accounting manager.
C. Sales manager.
D. Purchasing manager.
Answer (D) is correct.
The materials price variance is the difference between the standard price and the actual price paid for
materials. This variance is usually the responsibility of the purchasing department. Thus, the
purchasing manager has an incentive to obtain the best price possible.
18When items are transferred from stores to production, an accountant debits work-in-process and
credits materials accounts. During production, a materials quantity variance may occur. The materials quantity
variance is debited for an unfavorable variance and credited for a favorable variance. The intent of variance entries
is to provide
A. Accountability for materials lost during production.
B. A means of safeguarding assets in the custody of the system.
C. Compliance with GAAP.
D. Information for use in controlling the cost of production.
Answer (D) is correct.
One step in the control process is measurement of actual results against standards. For example, the
standard quantity of materials for a given output is established prior to production. If the actual
materials usage exceeds the standard, the variance is unfavorable and corrective action may be needed.
19Which of the following is least likely to cause an unfavorable materials quantity (usage) variance?
A. Materials that do not meet specifications.
B. Machinery that has not been maintained properly.
C. Labor that possesses skills equal to those required by the standards.
D. Scheduling of substantial overtime.
Answer (C) is correct.
An efficiency, or usage, variance for materials occurs when usage differs from the standard.
Unfavorable variances occur when actual usage is greater than standard. Labor whose skill is
commensurate with materials usage standards should achieve standard materials usage; that is, little or
no variance should arise
20Which department is typically responsible for a materials price variance?
A. Engineering.
B. Production.
C. Purchasing.
D. Sales.
Answer (C) is correct.
Responsibility for variances should bear some relationship to the decision and control processes used.
Materials price prices should be the responsibility of purchasing management.
22A company uses a standard-costing system in relation to its manufacture of scarves. Each finished
scarf contains 1.5 yards of direct materials. However, a 25% direct materials spoilage, which is calculated based on
input quantities, occurs during the manufacturing process. The cost of the direct materials is $2.00 per yard. The
standard direct materials cost per unit of finished product is
A. $2.25
B. $3.00
C. $3.75
D. $4.00
Answer (D) is correct.
If 1.5 yards remain in each unit after spoilage of 25% of the direct materials input, the total per unit
input must have been 2 yards (1.5 ÷ 75%). The standard unit direct materials cost is therefore $4.00 (2
yards × $2).
A manufacturer of radios purchases components from subcontractors for
assembly into complete radios. Each radio requires three units each of Part X, which has a
standard cost of $2.90 per unit. During June, the company had the following experience with
r espect to Part X:
Units
Purchases ($36,000) 12,000
Consumed in manufacturing 10,000
Radios manufactured 3,000
Question: 24Assuming that budgeted and actual radio production was the same, the amount that will be shown
on a static budget for Part X usage during the month of June is
A. $26,100
B. $27,000
C. $29,000
D. $36,000
Answer (A) is correct.
The 3,000 radios require three units each of Part X, a total of 9,000 units. At a standard unit cost of
$2.90, the 9,000 units will total $26,100.
25A company has a raw material price variance that is unfavorable. An analysis of this variance
indicates that the company’s only available supplier of one of its raw materials unexpectedly raised the price of the
material. The action management should take regarding this situation should be to
A. Negatively evaluate the performance of the purchasing manager.
B. Negatively evaluate the performance of the production manager.
C. Change the raw material price standard.
D. Ask the production manager to lower the material usage standard to compensate for higher material costs.
Answer (C) is correct.
Since there is only one source for the raw material, the standard cost should be changed to reflect the
firm’s true situation