Development Appraisals Level 1 Flashcards

1
Q

What is a Section 106

A

A site specific legally binding agreement with a landowner as part of the grant for planning permission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a CIL?

A

A tariff based charge set by local authorities on new development

can contribute to schools, health services, tansport improvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between CIL and S106

A

S106 is negotiable and decided on case by case basis where CIL is a fixed charge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What costs are associated with a development appraisal?

A

Site Preparation
Planning Costs
Building Costs
Professional Fees
Contingency
Finance
Developers Profit
Marketing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is included in site preparation?

A

Demolition
Site Clearance
Levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included in Planning costs?

A

section 106
CIL
planning application
local planning policy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is market standard for professional fees?

A

10-15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is market standard for contingency?

A

5%-10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why does contingency vary?

A

reflects risk of the project, for example if site didn’t have planning permission / movements in build cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the three elements a developer might need finance for?

A

Site Purchase
Total Construction
Holding Costs - voids until disposal of scheme (rates s/c)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is financing calculated for a site purchase?

A

straight line basis using compound interest
finance is spread equally over development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you calculate finance required for construction period

A

assume total construction costs over half of the time period using S curve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an S curve?

A

reflects when monies will be drawn down, assumes total costs over half time period reflected in S curve, beginning of the development costs will be lower as planning permission and design is undertaken, then peaks through construction and comes down nearer to completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate finance for ongoing holding costs?

A

From completion to disposal, straight-line and compounded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is developers profit?

A

the percentage of the GDV that developer requires as a return

if a project is more risky - higher return for taking on more risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What level on debt finance is assumed and why?

A

100% debt finance because we can’t assume clients equity because each borrower will borrow at different rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the main two methods of funding?

A

Debt financing - loaning money from bank

Equity - own money used

18
Q

What is the typical Loan to Value ratio (LTV)?

A

60:40

19
Q

What are the different types of Loans?

A

senior debt - first level loan

mezzanine finance - additional finance (higher interest)

20
Q

What is the Bank of England base rate?

A

5.25%

21
Q

What is a swap rate?

A

Fixed rate with profit margin on top

22
Q

What is the difference between a development appraisal and a residual appraisal?

A

development appraisal establishes viability

residential valuation to assess market value of site

23
Q

What is the RICS VIP 12 Valuation of Development Land?

A

Provides a framework for a consistent approach to the valuation of development land

covers site inspection
- extent of site
- flood risk
- shape of site
- any matters that could increase costs such as poor access
- party wall / boundary issues

  • variables that can influence site value
  • market demand
  • supply
  • competing developments
  • build costs

development programme assessment
- pre construction
- construction
- post construction

24
Q

What variables can influence site value?

A

market demand
location
supply
competing developments
environmental factors
build costs
planning
timescales

25
Q

What is affordable housing

A

local planning authority makes provisions to meet local demand and need for affordable housing

26
Q

Why is affordable housing important?

A

Improves quality of life, better health, financial stability and population diversity

27
Q

How is CIL calculated?

A

multiplying the new floor space that a development will be creating by the relevant CIL rate

28
Q

What is a sensitivity analysis?

A

re-calculate the appraisal with different assumptions on inputs, for example an increase in build costs or a decrease in gross development value, and seeing what effect this has on the profit measures.

29
Q

What are the different types of CIL?

A

Mayoral CIL - finance the Elizabeth line
Borough CIL -support local infrastructure

30
Q

what are the key components of a residual appraisal?

A

Site preparation, planning, build costs, professional fees, contingency, developers profit, marketing fees, finance

31
Q

What is the difference between MCIL and CIL?

A

MCIL is charges on top of CIL for the up keep of the Elizabeth Line.

32
Q

what stages of the development process might the developer need finance for?

A

Purchase of the site, construction and holding of the site

33
Q

What were the tariff rates for your residential development?

A

£50 sq m MCIL
£500 sq m CIL

34
Q

When might mezzanine finance be used?

A

to fill the gap between a developer’s equity and senior debt.

For example, a senior debt lender is able to lend 70% of the cost of a project, but the developer may only want to put 10% of their own equity into the project. The remaining 20% can be provided by a mezzanine lender.

35
Q

If all the build costs were at the start over the same time how would this affect finance?

A

finance would be higher because you would be paying more interest.

36
Q

What are the different types of sensitivity analysis?

A

simple sensitivity - key variables (GDV, costs, finance)

scenario analysis - change scenarios, development content, timings, phasing.

37
Q

What is yield on cost?

A

rental income divided by costs (build costs plus site costs) expressed as a percentage

38
Q

Developers profit?

A

GDV less costs = profit

profit as a percentage of the profit.

will vary depending on risk / planning.

39
Q

would a geared or ungeared IRR be higger?

A

geared as uses debt

40
Q

what does straight line basis mean?

A

costs are evenly spread over time