Design Economics and Cost Planning Flashcards

1
Q

What is BCIS?

A

The Building Cost Information Service, this provides cost and price information on a range of different projects and materials in the construction industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where does BCIS data come from?

A

Data comes from real life projects, where members of the construction industry provide real project cost information that once reviewed by BCIS staff is uploaded into the vast database.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Take me through the RIBA stages of cost planning.

A

Stage 0: Strategic Definition

Unlikely an estimate will be issued at this stage.

Stage 1: Preparation & Brief –

Likely to be an estimate based on functional unit method – Formal Cost Plan 1

Cost limit agreed with client

Feasibility estimate carried out

Stage 2: Concept Design –

Elemental Cost Plan based on Cost/ m2 GIFA

Cost based on cost analysis of similar previous projects

Stage 3: Spatial Coordination –

Elemental Cost Plan, measured from drawings where possible – Formal Cost Plan 2

Cost/m2 GIFA applied where sufficient detail not available

Stage 4: Technical Design –

Updated Elemental Cost Plan – Formal Cost Plan 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What factors need to be taken into account when using secondary source data?

A

Costs may need updated to account for location and time factors, this can be through the use of the tender price index which charts the movement of tender prices.

The formula: New Index – Old Index, Over Old Index – This gives the percentage uplift to be applied to the sample project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What other sources of cost data are there?

A

Price Books

Trade Journals

In house Information i.e. previous bills of quantities and cost plans etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main drawback of using historical data?

A

Market Trends

Out of date

Not having a complete knowledge of the historical data

Inaccuracies and inconsistencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between a feasibility estimate/order of cost and a cost plan?

A

A estimate is a forecast of possible cost of a building based on historical data, in the case of a feasibility its purpose is to determine whether the project is financially viable.

Cost Plans provide a breakdown of the total estimated cost and show the money is to be spent on different elements of the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which NRM is applicable to cost planning?

A

NRM1 – Order of Cost Estimating and Cost Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What type of ‘exclusion costs’ are there?

A

Common exclusions are:

Asbestos

Professional Fees

Vat – Different client will incur difference levels of VAT

Loose fixtures and fittings

Inflation

Site acquisition costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When looking at affordability of a project what client/stakeholder factors do you take into account?

A

It is important to inform the client of was the budget estimate includes and excludes.

For example, common exclusions are:

  • Professional Fees
  • Vat – Different client will incur difference levels of VAT
  • Loose fixtures and fittings
  • Inflation
  • Site acquisition costs

The client should therefore be advised that the total estimate provided by the QS, may not contain certain costs that he will incur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an elemental cost plan?

A

Cost Plans provide a breakdown of the total estimated cost and show the money is to be spent on different elements of the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Life Cycle Costing?

A

Life cycle cost is the cost of a building throughout its life taking account of initial costs and all future costs, e.g. maintenance, operation and occupancy costs, as well as end of life costs.

Life cycle cost calculations are an attempt to price as many as possible of the factors affecting the value of a building and to bring them into a single cost. This cost can then be compared with other design solutions, taking into account factors such as appearance, comfort and convenience, which are difficult to price and depend on personal judgement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is whole life costing?

A

The whole life cost includes the life cycle cost plus other costs such as the cost of the site, cost of financing the project, etc.

Whole life costs therefore relate to the overall development, whereas life cycle costs relate to the building only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What document details how a cost plan is to be created and the rules associated?

A

NRM 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the 3 methods detailed in this document for compiling a building works estimate?

A
  1. Functional unit method
  2. Floor area method
  3. Elemental method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

According to NRM1 what is an EUR?

A

Element Unit Rate

17
Q

According to NRM1 what is an EUQ?

A

Element Unit Quantity

18
Q

What are the RIBA stages?

A
  • 0 - Strategic Definition
  • 1 - Preparation and Brief
  • 2 - Concept Design
  • 3 - Spatial Coordination
  • 4 - Technical Design
  • 5 - Manufacturing and Construction
  • 6 - Handover
  • 7 - In Use
19
Q

What is a functional unit?

A

A functional unit is a term used to describe the desired unit of an accommodation in relation to a certain type of building and is used to calculate early stage cost estimates for those particular types of building. Examples of the type of building and the respective functional unit would be :

Hotel = Cost per bedroom
Hospital = Cost per bed
School = Cost per desk
Car Park = Cost per car parking space

20
Q

What is GIFA? What should you measure for that? Does it include the atrium?

A

GIFA is the gross internal floor area, it is the area of the building measured to the internal face of the perimeter walls at each floor level. According to RICS Guidance Note - Code of Measuring Practice all atria, with clear height above, are to be measured at base level only, meaning that where they occur over multiple floors, they should be excluded on upper floors and included only on the base floor.

21
Q

What is buildability?

A

The simplest way to describe buildability is in terms of deigning and constructing, in that where designers think, contractors do, buildability is the integration of the thinking process and the doing process giving a practical rationale to the design process.

22
Q

What is a TPI?

A

A Tender Price Index, Tender Price Indices reflect changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions – compared against base rates

23
Q

What is a PC Sum?

A

A PC sum is a Prime Cost sum. PC Sums are a sum of money included in a unit rate to be expended on materials or goods from suppliers, they are supply only rates for materials or goods where the precise quality of those materials and goods are unknown. PC Sums exclude all costs associated with fixing or installation, and design fees, preliminaries and overheads and profit for both main and sub contractors.

24
Q

When is the Elemental method of building works estimate mentioned in NRM1 used and how is it calculated?

A

A means of determining a budget. Provides an order of cost estimate based on an elemental breakdown. Calculated using element unit quantities and element unit rates.

Used when you have more drawing information so you are able to identify works specific to the project.

25
Q

When is the Floor Area method of building works estimate mentioned in NRM1 used and how is it calculated?

A

A means of calculating the total building works estimate (unit rate x GIFA). Also used for benchmarking similar projects.

Used for high level, early inception cost plans.

How is it calculated: By multiplying EUR’s and EUQ’s (which is your GIA or NIA) to make a Building Works Estimate.