Design Economics and Cost Planning Flashcards
What is a cost plan risk allowance?
NRM1 definition
- Quantitative allowance set aside as precaution against risk and future requirements, to allow for uncertainty of outcome
How do you quantify risk on a cost plan?
- Benchmark from similar projects, consider any abnormals (% allowance)
- Risk register as design develops to work out expected monetary value
What are some key reasons for cost overrun on a project?
- Ambiguous client brief
- Changes in later stages of project
- Project risk not properly managed
- Inadequate management of control and change processes
- Design not coordinated
- Changing external factors / market conditions (inflation, pandemic, legislation updates)
- Unsuitable selection of procurement strategy
- Statutory authority influences (i.e. onerous planning permission conditions)
What allowance would you make for contractor OH&P in the cost plan?
% varies, depending on:
- Location
- Perceived level of risk
- Project type and value
- Market conditions
How do you take account of the project location and why?
- Look at BCIS regional indices to make adjustment
- Done to recognise construction price differences in different locations (i.e. London compared to some places up north)
What’s meant by benchmarking?
- Use of historical data from projects of a similar nature
- Comparison / check for cost planning purposes
- Highlight if price is in line with expected values
What are the risks of benchmarking?
- Not properly considering abnormal - data obtained isn’t accurate
- Data doesn’t include for certain items (i.e. external drainage could be on roof / sometimes external works)
- Old projects may not be reflective of current market conditions
What are some typical design ratios?
- NIA to GIA ratio
- Wall to floor ratio
- Glazing to external wall ratio
- Split between 1, 2, 3 bed apartments
- Units per core
What efficiencies would you expect with the above ratios?
Depends on nature of project
- Net to gross ~80%
- Wall to floor ~85%
- Glazed to solid ext walls ~ 30%
- Split between 1, 2 and 3 bed apartments ~50/35/15
- Units per core ~ 6-8nr
How would you improve your NIA:GIA ratio?
- Less partiontioning
- Efective M&E planning to reduce Service Areas
- Reduction in common areas like lobbies, corridors, staircases
How would you improve your wall:floor ratio?
- Simplify Building Shape
- Increase Floor Size
- Reduce Floor Height
- Incorporate Shared Walls
What would you consider when looking at a glazed:solid wall ratio?
- Building use
- Requirements for thermal performance
- More glazing means more natural ventilation and potential internal temp control
What is the difference between an order of cost estimate and a cost plan?
- An order of cost estimate is prepared earlier on in the design process typically between RIBA Work Stages 0 to Stage 2.
- This is when the level of design information is more limited and allows a cost estimate to be prepared on a cost per m2 or cost per functional unit basis.
- A cost plan is produced typically at each RIBA Work Stage from Stage 2 onwards.
- As the design progresses more information can be included to eventually breakdown each element into its component’s parts.
What is the difference between cost and price?
- The cost is the total cost of labour, plant, materials and management deployed for a specific activity.
- The price is the amount a purchaser or client will pay for an item or product and is made up of the cost plus the main contractor’s profit margin.
How do you proceed if the cost plan exceeds the project budget?
- I would analyse the costs to assess the source of the increase and identify whether any element of work is abnormally high against the order of cost estimate.
- When the reason for the overspend is identified I would then look to propose value engineering options to my client and design team to bring the forecast back in line with the project budget.
What is buildability?
- Buildability is harnessing the contractor’s expertise and knowledge during the design stage to generate ideas for effective and efficient methods of construction.
What are the advantages of buildability?
- Buildability can result in better programming, sequencing and construction methods.
- A quicker more efficient programme can be achieved.
- Reduced capital and life cycle costs of the building can be obtained.
- The quality in the finished building’s performance and maintenance characteristics can be improved.
What is a wall to floor ratio?
- This shows the relationship between the wall area and floor area.
- It is used to show the cost efficiency of the building.
- The lower the ratio, the cheaper the building is to construct as there is less external envelope to construct in comparison to the floor area.
What is the most efficient shape?
- In theory a building with a circular floor plate building would offer the most efficient design as there is less wall to floor area.
- However a circular floor plate has a poor lettable floor area and is difficult to fit out therefore a square floor plate is considered to be the most efficient.
How would you prepare an estimate for M&E works?
- I would ask an M&E specialist surveyor to undertake the estimate.
- For feasibility estimates the M&E amount would be included in the m2 or functional unit rate.
What is a Section 106 agreement?
S106s are agreements between local authorities and developers that are negotiated in the context of granting planning consent.
What is construction to ‘shell and core’?
- Shell and core is the basic structure, services and envelope of the building.
- This normally includes the fit out of landlord and common areas for example the reception, toilets, lifts & stair cores.
- Base services are typically terminated at entry points to each of the lettable floor plates however life safety services infrastructure is normally provided.
What is a CAT A fit out?
- A CAT A fit-out provides a functional, yet unfinished space that tenants can then customize to their specific needs, often through a subsequent CAT B fit-out.
- This provides generic fit-out items to suit most developers for example basic fittings such as suspended ceiling tiles, raised floors, carpets, lighting and power distribution, and air conditioning / heating.
What is a CAT B fit out?
- A CAT B fit out overlays the CAT A provision with bespoke elements that are specific to the needs of the building’s user to enable the tenant to occupy and use the space.
- This would typically include partitions, power distribution to floor boxes, data cabling, artwork and branding, furniture, and kitchens.