An example when you carried out a VE exercise?
British Museum - Pre-Contract - VE Workshop with Client and Architect - establish what could be VE’d - window replace to repairs; kitchen replace to upgrade; external paving replace to repair and clean.
Give an example when you produced an estimate?
St Monica’s - Cost Plan 1 (RIBA Stage 2 Concept Design, not yet functionally coordinated) - Elemental take-off and GIA rates (services); high level specification; Risk Register; NRM 1 breakdown.
Give examples of preliminaries on an estimate you did?
British Museum - Benchmarked % from similar projects.
Give an example of life cycle costing on a project?
??????
Give an example of risks you priced on a project
Firemen’s Cottages
OoCE: Structural Remediation - Roof replacement (full costs to replace roof); underpinning (full costs for suspected foundations and remediation areas); decanting residents (full cost based on estimated number of weeks).
Cost Plan: Roof residual repairs (PSUM-allowance for possible repairs); Underpinning Residual unknown repairs (PSUM-allowance for exact requirements); decanting residents (Omitted-no risk remaining).
Give an example of risks post contract?
South Dock Marina - supplier/subcontractor availability (Performance Bond in place - in case contractor default)