Description of Project Documents and Processes Created Flashcards
Memorize document descriptions
Describe Activity Attributes Document
Detailed information about each individual activity / Define activities process
Describe Activity List
List of all the activities on the project / Define activities process
Describe Basis of Estimates
Describes how schedule, cost, and resource estimates were developed. Also includes their confidence level and ranges / Estimate activity duration, estimate costs, estimate activity resources process
Describe Change Log
Lists and describes the status of the change requests that is being processed or have been processed through the perform integrated change control process / Perform integrated change control process
Describe Assumption Log
List of all project assumptions and constraints. / Develop project charter process
Describe Cost Estimates
Cost of each individual activity / Estimate costs process
Describe Cost Forecasts
A prediction of how much the project will cost when it completes based on the current work. / Describe control costs process
Describe Duration Estimates
Amount of time needed to complete each activity on the project. / Estimate activity durations process
Describe Issue log
List of all issues on the project. Could include history type, description, priority, status, and resolution / Direct and manage project work process
Describe Lessons learned register
List of all lessons learned throughout the project / Manage project knowledge process
Describe Milestone list
Description of milestones on a project / Define activities process
Describe Physical resource assignments
Assignments of the physical resources to the activities or work packages / Acquire resources process
Describe Project calendars
A calendar view of what takes place on a day-to-day basis on the project. / Develop schedule process
Describe Project communications
Communicate in on the project by following the communications management plan / Manage communications process
Describe Project Schedule
A detailed breakdown of the work that needs to be done in order to complete the project. Will include a bar chart, milestone chart, and the project schedule network diagram. / Develop schedule process