Describe The Construction Planning Process Flashcards
Why must the land be checked before designing a building?
To check for restrictive covenants, right of ways, and building provision schemes
What secures the loan for a project?
The value of the land and completed building
What is the definition of “scheduling”?
The sequence of when and who will do the activities
What is an activity?
Things that must be accomplished to complete the project
What is a constraint?
It controls when or how activities are done
What is a critical path?
The path of activities that will create a logical order and allow the project to be completed in the shortest time frame
What are the possible problems with having materials delivered long before they are needed?
The material may get in the way of equipment, get damaged, or be stolen