Delivery of Service Flashcards
What does it indicate when a prospective client is using bidding as a method of selecting design professionals?
This means the client is very concerned with costs and may be likely to file a claim to save or recover money.
What must the architect do first before accepting the job?
Negotiate an agreement with the client that determines the scope of the work, fees required, and other aspects of the contract.
Should the architect accept work from the owner if the owner still has a contractual agreement with a former architect?
No, seeking to interfere with an existing contractual relationship is still often regarded as unethical and in some cases may also be illegal.
Should the project delivery method be confirmed before the architect’s agreement with the owner is made final?
Yes, because different delivery methods will demand different levels of design and detailing effort from the architect, and will determine the extent of the architect’s involvement in the project beyond the design phase.
What project delivery method is considered the traditional way?
Design-bid-build - in order to get the lowest cost.
There is considerable risk, though, that in the end the building will cost MORE than the lowest bid.
In terms of relationship between contractor, owner, and architect, what is the affect of bidding?
The contractor is in the role of adversary to the owner and architect.
Owner and architect want the highest quality building at the lowest cost.
Contractor wants to win the contract and still make a profit on construction.
What are two ways the contractor will try and make a profit?
- To achieve a low bid, a contractor will often underestimate the requirements of the project or base the bid on low-quality materials and labor, and then try to make up costs with change orders.
- They also may try and take advantage of discrepancies or ambiguities in the construction documentation to force change orders that could be considered errors or omissions and may be charged to the architect.
For a project scope, what is best advised for large and complex projects?
Construction manager who organizes multiple contracts, either with or without a fast-track schedule.
What can be implemented when there are many unknowns with the project?
Any of the project delivery methods may be employed using a cost-plus-fixed-fee price from the contractor, either with or without a guaranteed maximum price.
What project delivery method would be best for a low cost building?
Design-bid-build
What project delivery method would be best for the development of a government-owned civic building that calls for a structure with durable materials, energy-efficient systems, low maintenance, and low life-cycle costs?
A construction-manager-as-constructor method or an integrated project delivery
What is a way the architect can reduce risks involved in the design and building process?
The architect can help the owner select the best delivery method for the project.
To minimize risks during both design and construction, the architect may want the advice of someone with construction expertise.
This may suggest using a design-build team, hiring a construction manager (either as adviser or constructor), or creating an integrated project delivery arrangement.
What do the design-build, hiring a construction manager as adviser or constructor, and integrated project delivery all have in common?
These methods largely remove the adversarial relationship between architect, owner, and contractor in the traditional design-bid-build approach and encourage the team to avoid potential problems early in design as well as during construction.
What are the six main types of project delivery methods?
- Design-bid-build (DBB)
- Construction manager as adviser (CMa)
- construction manager as constructor (CMc)
- Design-build (DB)
- design-assist contracting
- integrated project delivery (IPD)
What is design-bid-build otherwise known as?
Design-award-build.
What is design-award-build?
It is DBB, one of the contractors bidding on the project is awarded the contract.
Generally, what does the architect do during the DBB method?
Architect designs the project and prepares the construction drawings and specifications.
What is the general “step-by-step” process that happens during the DBB method?
- Architect prepares the design, construction documents, and specifications.
- These documents are used as the basis for pricing the project and awarding a construction contract, either through competitive bidding or through negotiation with one contractor.
- The contractor then builds the project, while the architect provides contract administration services.
In DBB, does the owner have separate contracts with the contractor and architect?
Yes.
Why is the DBB method considered fairly simple?
It well defines all the roles and the work proceeds in a linear fashion, from selection of the architect to final build-out.
Coordination problems are minimized, contractual relationships are straightforward, and the owner can be quoted a fixed price before proceeding with construction.
What is the main disadvantage for DBB?
The design phase must be completely finished before the construction phase proceeds. This can be a problem if the owner needs the building quickly or if extended design and construction times result in higher financing costs.
If the contractor is not selected by negotiation, this method often leads to an adversarial relationship between the architect and contractor or between the owner and contractor.
What is the role of a CM?
The CM is generally hired by the owner, outside of the architect’s contract.
The CM advises on the constructability of the design as it is developed, provides early cost estimating and value analysis, completes project scheduling, assists with contract negotiations, manages multiple construction contracts and fast-track construction, makes early material purchases, and, in some cases, gives a guaranteed price and completion date.
What are two important disadvantages of using a CM?
- The CM is hired before the design work is finished, there is no competitive bidding on the cost of building the project, which may mean higher costs for the owner.
- There is a more complicated management structure due to having one more person on the design and build team.
How can the two main disadvantages of using a CM be reduced?
By allowing the contractor act as Construction Manager.