Definitions Flashcards

0
Q

Accepted Deliverables

A

Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Acceptance criteria

A

A set of conditions that is required to be met before deliverables are accepted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accuracy

A

Within the quality management system, accuracy is an assessment of correctness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Acquire Project Team

A

The process of confirming human resource availability and obtaining the team necessary to compete project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acquisition

A

Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activity

A

A distinct, scheduled portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity Attributes

A

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity Code

A

One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Cost Estimates

A

The projected cost of the schedule activity that includes the cost for all resources required to perform and complete the activity, including all cost types and cost components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity Duration

A

The time in calendar units between the start & finish of a scheduled activity. See also duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity Duration Estimate

A

A quantitative assessment of the likely amount or outcome for the duration of an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity Identifier

A

A short, unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other activities. Typically unique within any one project schedule network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Activity List

A

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Activity Network Diagrams

A

See project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Activity-on-Node (AON)

A

See precedence diagramming method (PDM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Activity Resource Requirements

A

The types and quantities of resources required for each activity in a work package.

16
Q

Actual Cost (AC)

A

The realized cost incurred for the work performed on a activity during a specific time period.

17
Q

Actual Duration

A

The time in calendar units between the actual start date of the scheduled activity
and either
the data date of the project schedule if the schedule activity is in progress
or
the actual finish date if the schedule activity is complete.

18
Q

Adaptive Life Cycle

A

A project life cycle, also known as change-driven or agile methods, that is intended to facilitate change and require a high degree of ongoing stakeholder involvement. Adaptive life cycles are also iterative and incremental, but differ in that iterations are very rapid (usually 2-4 weeks in length) and are fixed in time and resources.

19
Q

Additional Quality Planning Tools

A

A set of tools used to define the quality requirements and plan effective quality management activities. They include but are not limited to: brainstorming, force field analysis, nominal group techniques and quality management and control tools.

20
Q

Adjusting Leads and Lags

A

A technique used to find ways to bring project activities that are behind into alignment with plan during project execution.

21
Q

Advertising

A

The process of calling public attention to a project or effort.

22
Q

Affinity Diagram

A

A group creativity technique that allows large numbers of ideas to be classified into groups for review and analysis.

23
Q

Agreements

A

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.

24
Q

Alternative Analysis

A

A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project.