Dates Flashcards
Receipt of and addresses of notices in writing
+
Hand to hand, email, messenger
5 calendar days if mailed
same day (if work day) or next business day if sent at the end of the day
Role of the consultant Interpretations + findings must be made in how much time?
reasonable time
Applications for payment by CNTR?
CNTR submission of schedule of values?
monthly
+
15 calendar days (before first application of payment)
CO issue certificate of payment to → CNTR
10 calendar days
if CO does not agree with CNTR: O must write CNTR (if different amount) to
Signal disagreement in what delay?
Promptly
Contractor fails to comply w/requirements of the contract to a substantial degree, consultant makes formal notice; how many days for contractor de rectify the work ?
5 working days
CNTR → gives application of substantial performance → O + CO
How long for CO to verify validity of substantial performance?
20 calendar days
Owner shall pay accepted work (validated by certificate of payment) in what delay?
28 days max
CO + CNTR → set date for substantial performance
Immediate
Place holdback amount in joint account (O+CNTR) how many days before the expiry of the holdback period ?
10 calendar days
holdback prescribed by lien → payable CNTR (after expiration of holdback period stipulated by legislation)
10 working days
review application for final payment (by CNTR) → issue final → cert or payment
10 calendar days
if CO rejects final application for payment→ issue written notice to CNTR (reasons of rejection) (makes final visit)
Promptly in writing
O → pay the CNTR (after issuance of final cert of payment)
5 calendar days
CO → CNTR: written description in the form of a of proposed change in work CNTR → CO: will provide a method + time (adj contract $) in what delay ?
Promptly
O + CNTR → agree to adjustments (contract $ + time) → value included in application for payment in what delay ?
Promptly
O or CNTR → notice site conditions differ: concealed (subsurface) or other (not weather) (pre work start)
How long delay from first discovery must advise in writing to all parties ?
5 working days in writing
Concealed or unknown conditions:
CO → Investigate conditions → issue appropriate change instruction → CO or CD
Promptly
Delays:
No extension in contract time shall be made unless: notice in writing → given to consultant of valid reason (not fault of CNTR)
10 working days after the commencent of the delay
Delays:
No request of extension because of failure to provide SI until how many days after request ?
10 working days (after commencement of delays)
CO: makes claim for +$ contract price, or O: makes claim for credit
What kind of notice should be made for a claim ?
give timely notice for intent to make claim
Claims for a change in contract price:
CO: findings must be sent out to all parties. After having had made a judgment on the contract price
How many days after the receipt of the claim
30 working days
CNTR → fails to comply w/requirements contract (substantial degree) → CO (written statement to O+CNTR)
How many days to correct ?
5 working days to correct (immediately following notice in writing)
if work is suspended or delayed (under court or public authority) (not result of fault of contractor) how many days after the commencement of the delay can the contractor terminate the contract ?
20 working days and can terminate contract