Dates Flashcards
Receipt of and addresses of notices in writing
+
Hand to hand, email, messenger
5 calendar days if mailed
same day (if work day) or next business day if sent at the end of the day
Role of the consultant Interpretations + findings must be made in how much time?
reasonable time
Applications for payment by CNTR?
CNTR submission of schedule of values?
monthly
+
15 calendar days (before first application of payment)
CO issue certificate of payment to → CNTR
10 calendar days
if CO does not agree with CNTR: O must write CNTR (if different amount) to
Signal disagreement in what delay?
Promptly
Contractor fails to comply w/requirements of the contract to a substantial degree, consultant makes formal notice; how many days for contractor de rectify the work ?
5 working days
CNTR → gives application of substantial performance → O + CO
How long for CO to verify validity of substantial performance?
20 calendar days
Owner shall pay accepted work (validated by certificate of payment) in what delay?
28 days max
CO + CNTR → set date for substantial performance
Immediate
Place holdback amount in joint account (O+CNTR) how many days before the expiry of the holdback period ?
10 calendar days
holdback prescribed by lien → payable CNTR (after expiration of holdback period stipulated by legislation)
10 working days
review application for final payment (by CNTR) → issue final → cert or payment
10 calendar days
if CO rejects final application for payment→ issue written notice to CNTR (reasons of rejection) (makes final visit)
Promptly in writing
O → pay the CNTR (after issuance of final cert of payment)
5 calendar days
CO → CNTR: written description in the form of a of proposed change in work CNTR → CO: will provide a method + time (adj contract $) in what delay ?
Promptly
O + CNTR → agree to adjustments (contract $ + time) → value included in application for payment in what delay ?
Promptly
O or CNTR → notice site conditions differ: concealed (subsurface) or other (not weather) (pre work start)
How long delay from first discovery must advise in writing to all parties ?
5 working days in writing
Concealed or unknown conditions:
CO → Investigate conditions → issue appropriate change instruction → CO or CD
Promptly
Delays:
No extension in contract time shall be made unless: notice in writing → given to consultant of valid reason (not fault of CNTR)
10 working days after the commencent of the delay