Data Project Planning Flashcards

1
Q

Define the various roles in a data analytics project

A

Sponsor- provides funds
Program manager- directions
Project manager- manages triple constraints and gets data out to organization
Researcher- pushed the team to ask questions and identify problems
Data analyst-obtains and cleans data , makes a display of data and finds trends and outliers.
Unicorn is the ninja that knows everything?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define various roles of partners and stakeholders in projects

A

Stakeholder- anyone that has an interest or power in any decision or activity of the project.
Partners are the ones that carry out the specific project
3rd parties are customers or regulatory agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Critical Path and relationship to project timeline

A

CR is min time needed to complete all the project works. Delay on cp will delay project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain iron triangle

A

Iron meaning nonnegotiable, triangle is cost time and quality . Also known as triple constraints,