What is a Data Center?
A facility or room used to house mission critical computer systems and associated components fro companies and organizations.
Why use a Data Center? 6
- Geographic separation
- Power supply
- Cooling
- Usable space
- Fire rating
- Noise
Data Center Attributes (6)
- Cost
- Power
- HVAC - cooling
- Connectivity - Carriers, ISP, Own Fibre, Radio
- Security
- Access
Space
Carrier, Service Provider, Carrier Neutral, Own
Air Flow
Raised floor, close-coupled cooling on slab
Fire Suppression
none, Inergen, FM200, Novec 1230, Argonite
Cabling system
punchdown
plug - RJ45
UPS
Line-interactive Double-Conversion Online DC power Rotary
Protection
Power conditioners
Line filters
Mains Supply
Diverse grid fleeds
Gensets
Stationary fuel cell
Data Center Tiers Design?
Tier 1, Tier 2, Tier 3, Tier 4
Tier 1
Non redundant capacity components (single uplink and servers) (99.671%)
Tier 2
Tier 1 + Redundant Capacity components. (99.741%)
Tier 3
Tier 1 + Tier 2 + Dual Powered equipment and multiple uplinks. (99.982%)
Tier 4
Tier 1 + Tier 2 + Tier 3 + all components are fully redundant including storage, chillers, hvac, servers etc. (99.995%)
Min Clear Height
2.6m
Min floor loading
12kPA - 1200kg/sqm
General Data Centre Requirement “Entrance room”
Entrance room with man trap to prevent tailgating
General Data Centre Requirement “Access”
Biometric access
General Data Centre Requirement “door”
Wide access doors. Min door size 1m wide 2.13m high - other that man trap access
General Data Centre Requirement “Plant room”
Plant room for UPS, batteries, etc
General Data Centre Requirement “Service room”
Staging/service room/loading bay to allow access fro larger equipment and pallet jacket
General Data Centre Requirement “Air Condition”
22 degrees C +/- degree C
General Data Centre Requirement “Humidity”
30% to 60%
General Data Centre Requirement “Lighting”
Lighting 450 lux at 1.2m above finished floor level
Emergency lighting
General Data Centre Requirement “Power”
Standby power should assure 48 hours sustainability without re-fueling
General Data Centre Requirement “Security”
Integrated and alarmed BMS
Building security - integrated with site security, CCTV, coverage of entry and internal areas.
General Data Centre Requirement “Water”
Underfloor water detection
General Data Centre Requirement “Fire Rating”
Computer room envelope to have minimum 2 hour fire rating - to exclude fire from room.
Cooling the Data Centre
CRAC Hot/Cold Aisle Containment In Row Cooling In Rack Cooling Free Cooling
CRAC
Refrigerant based to produce pressure under floor
CRAH
Computer Room Air Handler to cool the room and move air within in.
Humidifier and Chiller
Humidifiers replace water loss before the air exits the AC units.
Chiller produces cold water for refrigeration process to either CRAC or CRAH.