Damages Flashcards
Hawkins v. McGee NH 1929, 2
Reliance/Expectation Damages
Key Facts:
∆ opreated on π’s hand and it made it worse, hairy hand. Does he get difference b/e what he was promised (perfect hand) and what he has, or just compensated for his harm.
Holding/Takeaway:
∆ promise was a contract and π should get expectation damages -> difference b/w current hand and perfect hand.
Dissent/Critique:
Isn’t this a windfall?
Groves v. John Wunder MN 1939, 6
Expectation Damages
Key Facts:
∆ intentionally breached contract/lease which required him to level land while he used it. Cost to level was $60,000, and value of leveled land was $12,160
Holding/Takeaway:
Cost of remedying the defect is the proper measure of damages. Tort concerned with fradulent breach. Holds ∆ to the contract
Dissent/Critique:
Recovery cannot be greater than actual loss. Windfall!
Peevyhouse v. Garland OK 1963, 13
Expectation Damages
Key Facts:
Same facts as Groves, except Peevyhouses actually live on the land.
Holding/Takeaway:
remedial work was “incidental” to the purpose of the contract which was to benefit from the coal. Econ. waste theory.
Landis v. Fannin OH 2011, 16
Expectation Damages
Key Facts:
Landis contract ∆ to build custom home. ∆ messes up “stain” for siding so it doesn’t match. Cost of repainting siding with solid color is $8,500, cost or putting on new “stained” siding is $66,906.
Holding/Takeaway:
Economic waste theory is tempered by the reasonableness test. Are the damages sought “reasonable.” [test taken from trespass tort cases]. Court find that they are because Landises wanted “Custom” home with “rustic” siding so the contractors must provide that in order to make them whole. Ugly fountain.
Acme Mills v. Johnson KT 1911, 22
Expectation Damages
Key Facts:
on April 26, π contracted to purchase wheat from ∆ on July 25 for $1.03 a bushel. On July 14-15 ∆ sold his wheat to Liberty Mills at $1.16 a bushel. He threshed on July 29th and did not deliver any wheat to π. Price July 25th = $1.00. Price July 29th < $1.00. Trial court $0 for breach of contract.
Holding/Takeaway:
Ct. appeals affirmed. Harm is calculated by comparing the general market price of the product on the date it would have been sold to the contract price.
Laurin v. DeCarolis MA 1977, 24
Expectation Damages
Key Facts:
∆ sold wooded area to π and removed gravel during sale w/o permission during closing of sale. Fair market value of gravel was $6480. PP: Trial court awarded π fair market value $6480 on torts theory of conversion. Ct. Appeals reversed, only had contract claim based on diminution in value of property, which was basically $0.
Holding/Takeaway:
π was entitled to the value of the gravel “as it lay in the land” without the added labor costs. Diminution of value was not appropriate b/c it did not measure the loss correctly, but neither is the π entitleled to the cost of the ∆’s labor.
Watt v. Nevada RR NV 1896
Reliance damages
Key Facts:
∆ negligently operated his train and set fire to π’s “backup” hay. Nearest hay market $10-12 a ton + 8.50 for bailing and transportation Trial judge gave π judgment and valued it at $10 a ton. ∆ appealed. Ct. appeals reversed and valued it at $3.50 (top market price - bailing and transportation costs.
Holding/Takeaway:
TORTS. No recovery for hay. It did not have value because the need for it is conjectural and π did not in actuality replace it. Can recover for the hay press with transportation costs.
Strouth v. Pools by Murphy and Sons, Inc., CT, 2003, p,797
Breaking Promises
Homeowners contracted for the installation of a peanut-shaped pool but the pool company excavated for a kidney-shaped pool, and the homeowners sued for breach of contract. A material breach of a contract by one party justifies the other party’s termination of the agreement.
Plante v. Jacobs, WI, 1960, p.799
Breaking Promises
K to build house; minor defects: wall between kitchen and living room 1 ft in wrong way. Ct: substantial performance (performance meets essential purpose of K) even if it ≠ completely in compliance. P should recover K price – deduction for small issues of repair. Reconstructing wall would be economic waste b/c wall does ≠ effect value of house. D did ≠ ask for cure during construction of stock house (≠ customized). Measure damage under cost-of-replacement or diminution of value rule depending on nature/magnitude of defect.
Printing Center of Texas, Inc. v. Supermind Pub. Co., TX, 1984, p.814
Breaking Promises
Sued for refund of deposit made under K to print books b/c they failed to conform to K. UCC 2-601 = perfect tender rule – buyer’s can reject goods that do ≠ conform to K in every respect (complete performance). Sample provided that induced K creates an express warranty that the whole of goods will conform. Implied warranty of merchantability as well.
Prescott & Co. v. J.B. Powles & Co., WA, 1920, p.816
Breaking Promises
Order for 300 crates of onion, only one ship sailing between Australia and San Fran, only allowed to order 240 b/c remainder suddenly taken up by US gov. Buyer refused acceptance, seller resold at lesser market value. Ct: delivery of goods must be exact quantity; no excuse b/c of govt b/c sued on K (full performance must be shown). Buyer could have rendered performance impossible or a waiver.
Ramirez v. Autosport, NJ, 1982, p.817
Breaking Promises
Allow rescession only for material breaches now + opportunity to cure. UCC 2-601: mitigation w/ good faith; 2-601, excluding installment Ks; 2-612: broad definition of installment K, test of materiality
Beck & Pauli Lithographing Co. v. Colorado Milling & Elevator Co., 8th Cir. 1892, p.818
Breaking Promises
Extensive order of engraved letterhead, bills, etc. Proof submitted and approved; finished products shipment, arriving 2 months later, rejected. Ct: time of performance ≠ necessarily essence unless express provision indicates condition. In K for artistic skill and labor, time clauses are ≠ strictly construed. Articles ≠ sellable to other buyers. No indication of injury.
Plateq Corp. of North Haven v. Machlett Labs., Inc., CT, 1983, p821
Breaking Promises
Two lead covered steel tanks constructed to P’s specifications. K provided tanks would be tested for radiation leaks before acceptance and P would need to cure. When performance substantially completed, D noted some deficiencies. P promised to correct and D communicated general acquiesce to proposed tender (truck by for pickup). Then, D cancelled. Ct: D accepted by signaling willingness to take tanks despite nonconformities. Could have demanded cure UCC 2-508, or revoked under UCC 2-608 (substantial impairment of value), but accepted after inspection (failed to make effective rejection) – liable for full price under UCC 2-607(1). Rejection ≠ particularized UCC 2-605 (prevent a cure). Tank ≠ sellable on open market, so seller gets K price minus salvage.
Worldwide RV Sales & Service v. Brooks, IN, 1989, p.825
Breaking Promises
K to purchase motor home; agreed it would have two roof AC units; when Brooks arrived, vehicle only had one roof AC. Refused acceptance; Worldwide offered to cure by installing two ACs (leaving hole in roof); declined. Ct: refusal proper under UCC 2-601 (can≠ claim 2-508: nonconforming delivery or substitution).
Fortin v. Ox-Bow Marina, Inc., 1990, p.825
Breaking Promises
Months after taking delivery of Bayliner, P revoked acceptance and sued for refund. Ct: support for findings of minor defects, but series of defects, even if some cured, can shake buyer’s faith in goods -> sub impairment of value. Delay of revocation ok if buyer/seller in constant communication/seller makes repeated assurances of cure.
Jacob & Youngs v. Kent, NY, 1921, p.802
Breaking Promises
Owner did ≠ complain of defect for 9 months. K required that pipes be from Reading, but thy did ≠ use that type. P sued to recover balance from D. Ct: omission of pipe ≠ willful and there was no diff in quality, etc. (ev excluded from trial), should be atoned for by allowance of damage (≠ a breach of condition followed by forefeiture). If change was so dominant/pervasive, it would frustrate purpose of K, but degree of deviation ≠ great here and parties were silent as to importance (says Cardozo.) Two options: market value difference or cost of replacement.
Reynolds v. Armstead, CO, 1968, p.805
Breaking Promises
π contracted to apply brick veneer to ∆’s house. Failed to do so properly. Material breach, but still entitled to quantum meruit
Hadden v. Consolidated Edison Co. of New York, NY, 1974, p.806
Breaking Promises
After an employee’s retirement, employer discovered facts that would have allowed for “for cause” termination and revoked his pension. Ct. found that employee’s performance was substantial given that the breach was in some of the employment years, not all of them, and the breach doesn’t impair the overall work.
K&G Const. Co. v. Harris, MD, 1960, p.737
Breaking Promises
GC in K w/ sub for excavating. Progress payments for each month of K. D accidentally bulldozed wall; GC w/held progress payment; D refused to work. Ct: Performances were conditioned on promise of others; where total price fixed for K, work ≠ divisible by progress payments. Sub materially breached promise of workmanship when bulldozing the wall, but GC treated it as partial breach by allowing sub to continue work after he messed up the wall meant Kor treated nonperformance as partial breach. Sub defaulted against by refusing to continue K
Stanley Gudyka Sales Co. v. Lacy Forest Products Co., 7th Cir., 1990, p.740
Breaking Promises
Dealer in wood products K for services of similar dealer; would split profits, could terminate K for “just cause.” Lacy terminated b/c he failed to promptly remit commissions ($3000), but Lacy owed Gudyka ($46,000) Ct: found for Gudyka. Self-help available only where termination is in proportion to the need for accountability and breach is material/≠ insignificant. W/out notice and opportunity to cure, there is no just cause. Doctrine of conditions ≠ a tool, which will permit a party to use an insignificant breach as a pretext for avoiding Kual obligations.
Wholesale Sand & Gravel, Inc. v. Decker, ME, 1993, p.735
Breaking Promises
Agreed to install driveway on Decker’s property w/ no completion date specified; payment w/in 90 days of completion. Began work immediately, but difficulties b/c ground wet, so waited. D contacted P re: lack of progress; P reassured, but still failed to perform. Ct: anticipatory repudiation = “definite and unequivocal manifestation of intention on part of repudiator to ≠ render promised performance when time fixed for it arrives. May be through words or conduct. May also excuse non-occurrence of condition. [Could have demanded assurance 2-609, R2K §251]
Hathaway v. Sabin, VT, 1891, p.810
Breaking Promises
D to furnish an opera house for a concert and pay $75 after the entertainment. Weather horrid and D decided to ≠ open/heat hall even though P eventually arrived; P = failed to furnish the hall. Ct: party who becomes involved in difficulties that he ≠ responsible for should ≠ be deprived of benefits of K b/c other party assumes difficulties are insurmountable if he can perform ultimately. D decided against performing too early ≠ for D to decide that damages were less than amount he agreed to pay when P incurred everything on his part and was prevented from earning compensation solely b/c of D’s failure. AoR should be on concert promotor?