Damages Flashcards

1
Q

Robinson v Harman (1848)

expectation measure

A

FACTS: H wrote to R offering him a 21-year lease of a dwelling house in Croydon. He subsequently changed his mind and refused to complete the lease when he discovered the property was worth more than the agreed price. The property was actually vested in trustees and H was only entitled to a portion of the property. R brought an action for damages.

JUDGEMENT: R successfully recovered damages for his expenses and for the loss of the bargain.

PRINCIPLE: “Where a party sustains loss by reason of a breach of contract, he is, so far as money can do it to be placed in the same situation, with respect to damages, as if the contract had been performed.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Ruxley Electronics and Construction Ltd v Forsyth [1996]

A

FACTS: R agreed to build a swimming pool at F’s home. The contract specified the depth of the pool was to be seven feet and six inches. R completed the pool to a depth of six feet and nine inches. F brought an action for breach of contract, claiming the cost of rebuilding the pool to the specified depth.

JUDGEMENT/PRINCIPLE: F could not recover the cost of re-building because this would be totally out of proportion to the loss he had suffered. He could recover £2,500 for loss of amenity but the law must cater for cases where full performance of the promise would vastly exceed the loss which had truly been suffered. The pool was, in fact, worth no less because of the breach but to award nothing would render the contractual promise illusory, and so a nominal award was appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CCC Films v Impact [1985]

Reliance measure

A

FACTS: D gave C licence to exploit, distribute and exhibit 3 films in some countries, for $12,000. D promised to insure tapes and post by recorded delivery. D sent tapes uninsured and by ordinary post; tapes never arrived. C claimed $12,000 wasted expenditure, but could not prove it would have been recouped

JUDGEMENT:

(1) C has an “unfettered choice” between expectation and reliance measure.
(2) A claim for wasted expenditure does not require C to show that C suffered no or little loss or is unable to prove loss.
(3) However, wasted expenses can only be claimed insofar as they would have been recouped without breach. C generally bears the onus of proof.
(4) Where D’s breach prevented C from exploiting the contract’s subject matter, D must prove that C’s expenses would not have been recouped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Anglia Television Ltd v Reed [1972]

A

FACTS: R had agreed to play the major role in a TV series which was going to filmed by A. However, before taking part, he abandoned the television series and decided not to take part. He therefore terminated the contract and A sued him for breach of contract and reliance loss because in preparation for filming they had incurred a certain amount of expenses amounting to £2750

JUDGEMENT: A won the case

PRINCIPLE: C may even claim wasted expenditure incurred before the contract was made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

C and P Haulage v Middleton [1983]

A

FACTS: M had a licence to occupy C&P’s premises for 6 months, provided that at the end of the 6 months, any improvements added to the building were not removed. After being evicted 10 weeks prior to the end of the 6 months, could Middleton claim damages for the improvements made to the building?

JUDGEMENT: Held that M could not claim. After the breach, M moved back to his house and worked rent free, therefore he would be unjustly enriched if damages were awarded; at the end of the 6 months, he would have had to leave the ‘improvements’ anyway.

PRINCIPLE: The reliance measure cannot be used to escape from a bad bargain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Attorney General v Blake [2001]

A

FACTS: A double agent, traitor and criminal residing in the Ukraine published a book of his memoirs contrary to the Official Secrets Act

JUDGEMENT: Even though the primary aim is to award damages as compensation, it may be possible for the government to claim as damages a portion of the profit that the contract breaker makes.

PRINCIPLE: Exceptional circumstances allow deviation from the usual compensatory principle to account for profits. Next best alternative to an impossible criminal conviction where a matter of national security was concerned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

AB Corp v. CD Co (The “Sine Nomine”) [2002]

A

JUDGEMENT: No restitution for breach of charter party, as profit maximising legitimate

“It is by no means uncommon for commercial contracts to be broken deliberately because a more profitable opportunity has arisen. International commerce on a large
scale is red in tooth and claw. Our solution to the present problem is that there should not be an award of wrongful profits where both parties are dealing with a marketable commodity—the services of a ship in this case—for which a substitute can be found in the market place. In the ordinary way the damages which the claimant suffers by having to buy in at the market price will be equal to the profit which the wrongdoer makes by having his goods or his ships’ services to sell at a higher price. It is in the
nature of things unlikely that the wrongdoer will make a greater profit than that. And if he does, it is an adventitious benefit which he can keep. The commercial law of this
country should not make moral judgments, or seek to punish contract-breakers; we do not, for example, award triple damages, as in the USA.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Wrotham Park Estate Co v Parkside Homes Ltd [1974]
(The court talked about possibility of claiming the profit of the contract breaker on the basis of the hypothetical release of the contract)

A

FACTS: The owners of an estate sold part of their estate to a developer. They put a restriction in the contract (i.e. a covenant) which restricted the right to develop a portion of the estate and they had to obtain the permission of the estate manager first if they wanted to develop. The estate owner died and everything passed on. The area was eventually sold to a local authority which obtained planning permission – this was eventually sold to the defendant. The heir to the estate reminded the defendant that there was still an existing covenant. The defendant breached the covenant and built houses and therefore the plaintiff (i.e. claimant) sued asking for the demolition of the houses and, if this was not possible, for a portion of the profit

JUDGEMENT: The court allowed the plaintiff to claim a portion of the profit on the basis that they could have, if they had wanted, tried to obtain a release from the covenant by negotiating a change in the price. The court held that 5% in this hypothetical release was roughly the right amount and therefore the hypothetical release (the 5% which the defendant could have negotiated to circumvent the covenant) was the loss that the plaintiff had suffered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Weld-Blundell v Stephens [1920]

Causation

A

FACTS: The defendant had negligently leaked some documents to a third party, which contained libellous statements written by the claimant about the third party.
The third party sued in libel and won. Could the claimants recover from the defendants for their negligence?

JUDGEMENT: Held that they could not. The libellous statements were intentional and had broken the chain of causation.

PRINCIPLE: If the “but for” test is satisfied, the defendant may still escape liability on the ground that an unforeseeable act of a third party broke the chain of causation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Hadley v Baxendale (1854)

Remoteness

A

FACTS: C owned a flour mill. C and D contracted for the purchase of another crankshaft, so the machine for the mill would work. The crankshaft was not delivered in a reasonable time which breached the contract. C sought money for loss of profit by suing D as his flour mill did not work without the crankshaft.

JUDGEMENT: The court did not award the entirety of the damages that they were claiming because it was held the loss that they had suffered was too remote. C had not told D that they wanted him to make a replacement crankshaft quickly. Thus, D could not be liable for the C’s losses because, in effect, D could not contemplate the C’s loss.

PRINCIPLE: Damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Hadley v Baxendale test for remoteness

A

Claims for damages can only be made where damages:

(a) Arise naturally from the breach, so will be compensated AND
(b) The losses that may fairly and reasonably be supposed to have been within the reasonable contemplation of the parties will be rewarded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949]

A

FACTS: C had a laundry business and wanted to expand their laundry business as there was a shortage of laundry services after the war. To do this they contracted with D to buy a boiler. It was agreed the boiler would be delivered on 5 June. The boiler was not delivered until November, which led to Victoria Laundry suing D for damages. They asked for the loss of business they would have had had they received the boiler on time and also claimed that had they had the boiler they would have been able to win a lucrative government contract so sued for this too

JUDGEMENT: Applying Hadley v Baxendale, the court only allowed the recovery of the losses of the business but they did not allow the loss of the lucrative contract from the government (even though they would have got it) as it was seen to be too remote. Even though Neman had specific technical knowledge (they knew that the boiler was going to be used for a very specific purpose) it was still not within the contemplation of the parties that the plaintiff would then bid for the government contract

PRINCIPLE: This case reformulated the Hadley case in terms of foreseeability, therefore applying similar standards to tort – but this was criticised in The Heron II case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Koufos v C Czarnikow Ltd, The Heron II [1969]

A

FACTS: A vessel was chartered to take a cargo of sugar to Basra where there was a sugar market. The charterers intended to sell the sugar immediately upon arrival in Basra. However, the vessel was delayed by 9 days by which time the price of sugar had dropped. The charterer therefore sued for the losses they have incurred and for the difference they would have been entitled to get upon arrival and what they got 9 days later which was considerably less. Question = was it foreseeable the plaintiff wanted to sell immediately and if the price of sugar dropped a loss would be suffered by the plaintiff?

JUDGEMENT: The charterer was entitled to recover the difference they would have been entitled to get upon arrival and what they got 9 days later. The reasoning of this was that even though the owner of the ship did not know that the charterer intended to sell the sugar straight away upon arrival, he knew the charterer was in the sugar business and knew the price of sugar varies so it was not unlikely that if there was a delay and the price of sugar dropped they could foresee their breach would cause the plaintiff a loss

PRINCIPLE: The court here (criticising the approach of the CA in Victoria Laundry v Newman Industries) said it is not possible in contract to have the same foreseeability test as in tort. So, in this case the House of Lords held that the defendant is only liable for those losses which he foresaw or could have foreseen at the time the contract was being made as not unlikely to result from the breach of contract – this approach is stricter than tort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The Achilleas [2009]

Remoteness reformulated/rationalised for exceptional cases

A

3 different rationales suggested – assumption of responsibility, foreseeability of loss, justice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Addis v Gramophone Co Ltd [1909]

Non-pecuniary loss

A

FACTS: C was employed by D. D breached his own contract by replacing C. C wanted damages for the defendant ruining his reputation and ability to find another job.

JUDGEMENT: No right to exemplary damages as that is only available in tort. Furthermore, it was impossible for the claimant to get damages for any emotional distress he suffered.

PRINCIPLE: Non-pecuniary loss is not generally recoverable in an action for breach of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Grant v Australian Knitting Mills Ltd [1936]

Australian case - non-pecuniary loss

A

FACTS: G was affected by dermatitis (skin rash) after wearing a pair of underwear he had purchased. The manufacturer negligently left a chemical, metal sulphite in the materials of the underwear. Grant had a contract with the seller, but he did not have a contract with the manufacturer, which he sued for negligence.

JUDGEMENT: Referred to Donoghue v. Stevenson and held that the injured party was successful.

PRINCIPLE: There are growing exceptions to non-pecuniary loss, personal injury being one of them.

17
Q

Bailey v Bullock [1950]

Non-pecuniary loss - physical inconvenience or discomfort

A

FACTS: A solicitor failed to take action to recover the claimant’s house. As a consequence the claimant and his wife had to move in with his in-laws for two years.

JUDGEMENT: Held that he was entitled to recover damages to reflect the inconvenience of having to live in overcrowded circumstances.

PRINCIPLE: Barry J emphasised that there is a distinction between mere annoyance or disappointment at the failure of the other party to carry out his contractual obligation and actual physical inconvenience and discomfort caused by the breach.

18
Q

Jarvis v Swans Tours Ltd [1973]

A

FACTS: J booked a 15 day skiing holiday over the Christmas period with Swan Tours. The brochure in which the holiday was advertised made several claims about the provision of enjoyment relating to house parties, a friendly welcome from English speaking hotel owner, a variety of ski–runs, afternoon tea and cakes and a Yodler evening. Many of these either did not go ahead or were not as described. J brought a claim for breach of contract based on his disappointment. At trial, the judge awarded him £30 damages on the basis that he had only been provided with half of what he had paid for and that no damages could be recovered for disappointment. J appealed.

JUDGEMENT/PRINCIPLE: Where a contract is entered for the specific purpose of the provision of enjoyment or entertainment, damages may be awarded for the disappointment, distress, upset and frustration caused by a breach of contract in failing to provide the enjoyment or entertainment.

19
Q

Farley v Skinner [2001]

A

FACTS: F instructed S to prepare a survey on a property he was considering purchasing. The property was 15 miles from an airport, and F specifically requested S to ascertain whether it would be affected by aircraft noise because he did not wish to live on a flight path. S reported the property was unlikely to be affected by aircraft noise. F purchased it and it was substantially affected by aircraft noise. He sought damages for breach of contract.

JUDGEMENT: F able to recover for his discomfort.

PRINCIPLE: Damages could be recoverable for the loss of a pleasurable amenity which may be of no economic value, if they are of importance to C. Recovery was not restricted to physical discomfort, and it was sufficient to show that the question of the amenity formed an important part of the contract.

20
Q

Kpohraror v Woolwich Building Society [1996]

A

FACTS: C was a self-employed importer and exporter of goods. He held a current account with D. C purchased some goods for £4,550 from a wholesale supplier who agreed to supply hm with the goods and ship them to Nigeria for resale. He paid for the goods by cheque, however the cheque was wrongly dishonoured. D corrected their mistake a day later. C brought an action for breach of contract and claimed general damages for loss of business reputation. The damages included a small allowance for loss of reputation in Nigeria. D admitted the breach but disputed the claim for loss of reputation.

JUDGEMENT/PRINCIPLE: CA lifted the rule of no recovery for general damages for damage to financial reputation which had previously only been available in relation to tradesman.

21
Q

Barclays Bank plc v Fairclough Building Ltd (No.1) [1995]

Cont negligence as a defence?

A

FACTS: B employed F to clean a roof which was made of corrugated sheets. F did not take any safety precautions when cleaning. The premises were contaminated with asbestos and needed extensive work to repair the damage. B brought an action in damages for the cost of the repair work on the basis of F breaching contractual terms. F argued that B had contributed to the negligence as B had not supervised F during the cleaning. B counter-argued that their claim was brought under contract law and therefore could not trigger a negligence claim under tort law. The trial judge held that F was at fault but that there was an implied duty to take reasonable care and therefore the defence of contributory negligence could be successful. The trial judge found that B was 40% at fault and that damages would be owed as per the Law Reform (Contributory Negligence) Act 1945, section 1 and section 4. B appealed this decision.

JUDGEMENT: The appeal of the bank was allowed and therefore F’s defence of contributory negligence was rejected. It was held that in circumstances where the defendant is in breach of a strict contractual clause, damages could not be reduced on the basis of contributory negligence.

PRINCIPLE: Confirmed that the 1945 Act applies to category 3, but not to category 1 or 2.

22
Q

Mitigation

A

(1) Where C fails to take reasonable steps to minimise the loss, C receives no damages for the extra loss that could have been avoided: Kaines (UK) Ltd v Österreichische Warenhandelsgesellschaft Austrowaren GmbH [1993]
(2) Where C takes unreasonable steps that increase the loss, C receives no damages for the extra loss so caused: Baxendale v London, Chatham, and Dover Railway Co (1874)
(3) The claimant can recover damages for extra loss caused by reasonable conduct: Banco de Portugal v Waterlow & Sons Ltd [1932]
(4) The claimant cannot recover damages for loss that has in fact been avoided: Cerberus Software Ltd v Rowley [2001]