DAA List of Dominion Codes Flashcards
TD7625GROD*
Pad mount transformer, 25 kVA, 19.9 kV to 120/240 volts
TD76100GROD*
Pad mount transformer, 100 kVA, 7.6 kV to 120/240 volts
TD1925GROD*
Pad mount transformer, 25 kVA, 19.9 kV to 120/240 volts
TD19100GROD*
Pad mount transformer, 100 kVA, 19.9 kV to 120/240 volts
KPTERM10
1 PH TERMINATION NON-ENERGIZED =<1/0
TD1916776*
Pad transformer stepdown deadfront, single phase, 167 kVA, 19 kV to 7.6 kV
TD1950076*
Pad transformer stepdown deadfront, single phase, 500 kVA, 19 kV to 7.6 kV
PDPC1T36BF
Precast box pad for single phase transfomers
FEEDTHRU
200 amp, large interface, 35 kV loadbreak bushings
AR27EBMOVGS
Arrester, 27 kV elbow (for 19 kV circuits)
FCUSLV
Fuse, current limiting, 200 amp, 250V 2 sleeve term., 4/0 al - (Code for 2 each address)
FEEDTHRU2
200 amp, small interface, 15 kV loadbreak bushings
PROTECAP200
Protective Static Cap, 35 kV
PROTECAP15KV
Protective Static Cap, 15 kV
AR10EBMOVTSM
Arrester, 10 kV elbow (for 7.6/7.2 kV circuits)
FI300UGL
Fault Indicator, 300 amp trip, 1 phase transformers (every fifth transformer)
KCPBLTERM10
Termination of primary cable into existing transformer pad
CND4S490D36
PVC Schedule 40 4” elbow 90° 36” radius
KOPEXISTTRF
Install Open Point into existing transformer pad
KCBLREARR
Use when splicing new primary into existing primary between devices
KFIEXISTTRF
Installation of fault indicator into existing transformer pad
TME10J3
Terminator Elbow, 21.1/36.6kV for 1/0 al., jacketed, 345 mil, cable
SD1TPVE
Single Phase Tap Switch
TME10J3
Terminator Elbow, 21.1/36.6kV for 1/0 al., jacketed, 345 mil, cable (quantity of 4 need)
FI300CRUG
Fault indicator, 300 amp trip, u.g. 1 ph. 1/0 cable -
SECPED
Secondary Pedestal
KTERMPED
Secondary termination non-energized =<1/0
FCU2SPD
Fuse, c.l., 200 amp, 250V, two 1-hole spade term. For pedestal - (Code for 2 each address)
DTC27GROD*
Dummy transformer cabinet, (27 kV elbow for 19 kV circuits)(10 kV elbow for 7.6/7.2 kV circuits)
KPTERM10
1 PH TERMINATION NON-ENERGIZED =<1/0
FI300CRUG
Fault indicator, 300 amp trip, u.g. 1 phase 1/0 cable - Dummy transformers
GROD4CUUG (15)
1-4 Ft. Copper Rod & Coupling
GRODCUUGF
Fixed Items Copper Rod, Each Location
KGRDROD
Labor code to install ground rods
GNDKITLC
GROUNDING KIT FOR SPLICE PITS
KTUNNEL2
GUIDE DRILL EXCAVATE 2 IN TUNNEL
KTUNNEL4
GUIDE DRILL EXCAVATE 4 IN TUNNEL
KTUNNEL6
GUIDE DRILL EXCAVATE 6 IN TUNNEL
KROCKDRL4
ROCK GUIDE DRILL (INCLUDE FOOTAGE’)
CND2SPOOL
HDPE 2”, Schedule 40, Conduit - (1/0, 4/0, #8)
CND4SPOOL
HDPE 4”, Schedule 40, Conduit - (750)
CND3SPOOL
HDPE 3”, Schedule 40, Conduit - (500)
KCND2TUNNEL
PULL 2” CONDUIT THROUGH TUNNEL
KCND3TUNNEL
PULL 3” CONDUIT THROUGH TUNNEL
KCND4TUNNEL
PULL 4” CONDUIT THROUGH TUNNEL
U10J3TUNOO
1/0 primary, guide drill from pole to pole
U10J3TUNOP
1/0 primary, guide drill from pole to pad
U10J3TUNPP
1/0 primary, guide drill from pad to pad
U10J3TUNOS
1/0 primary, guide drill from pole to splice
U10J3TUNPS
1/0 primary, guide drill from pad to stub up
U10J3TUNSP
1/0 primary, guide drill from splice to pad
U10J3TUNSS
1/0 primary, guide drill from splice to splice
U10J3TUNSP
1/0 primary, guide drill from splice to pad (OPEN/CLOSE Holes built into MU)
KPSPLICE10
1/0 SPLICE LABOR
SPL10J3
1/0 SPLICE KIT
KCBLSPK
DE-ENERGING EXISTING 1/0 PRIMARY LABOR (Test before splicing new into existing for safety)
KXHOLEAO
OPEN STANDARD SPLICE PIT 6’X4’X4’
KXHOLEAC
CLOSE STANDARD SPLICE PIT 6’X4’X4’
KPSPLICE10
1/0 SPLICE LABOR
SPL10J3
1/0 SPLICE KIT
KPPOTP
VDOT ROAD CROSSING ( POTHOLE TO LOCATE UTILITIES)
USGD50PAPD
UG 500 Secondary, guide drill from transformer to pedestal
USGD50PAOH
UG 500 Secondary, guide drill from transformer to pole
USGD50PDPD
UG 500 Secondary, guide drill from pedestal to pedestal (Not Standard Practice)
USGD75PAPD
UG 750 Secondary, guide drill from transformer to pedestal
USGD75PDPD
UG 750 Secondary, guide drill from pedestal to pedestal
BUSPLATE (3)
Secondary Busplate for 1P Transformers, 8 hole plate
LP50GD
500 service lateral guide drill from pedestal to meter w/ 3” riser
LP50GDPDSP
500 service lateral guide drill from pedestal to splice
LT50GD
500 service lateral guide drill from transformer to meter
LT50GDSP
500 service lateral guide drill from transformer to splice
LT40GD
4/0 service lateral guide drill from transformer to meter or jbox
LT40GDSP
4/0 service lateral guide drill from transformer to splice
LP40GD
4/0 service lateral guide drill from pedestal to meter (or jbox) w/ 2” riser
LP40GDPDSP
4/0 service lateral guide drill from pedestal to splice
LP40GDPDST
4/0 service lateral guide drill from pedestal to stub up
SEC2AL
2 Aluminum Entrance Cable
SEC20AL
2/0 Aluminum Entrance Cable, 100 amp meters (removal only)
SEC40AL
4/0 Aluminum Entrance Cable, 200 amp meters
LT50GD40SP
500 splice into 4/0 service lateral guide drill from Tranformer
USGD40PAOH
UG 4/0 Secondary, guide drill from transformer to pole
USGD50PAOH
UG 500 Secondary, guide drill from transformer to pole
USGD40PDOH
UG 4/0 Secondary, guide drill from pedestal to pole
USGD50PDOH
UG 500 Secondary, guide drill from pedestal to pole
SVCBRKWAY2
Service line breakaway
LT40GD
4/0 service lateral guide drill from transformer to meter or jbox
CND2S4
PVC Schedule 40 2”
KHT24
HAND TRENCH/BACKFILL 24 IN (include footage’)
KCNDTRNC* (2 OR 4)
PLACE CONDUIT IN TRENCH 2 IN OR 4 IN (include footage’)
KCBLTRNC* (2 OR 4)
TIEING EXISTING SVC DIRECTLY INTO TRANSFORMER
CND*S490D24 (2 OR 3)
PVC Schedule 40 2” elbow 90° 24” radius (2 or 3, Conduit size)
USL8DCUGDPAOH
8 service guide drill from transformer to street light
USL8DCUGDPDOH
8 service guide drill from pedestal to street light
USL8DCUGDPOPO
8 service guide drill from street light pole to street light pole