CSP, Lvl 6- Lessons 4,5,7,8 Flashcards

1
Q

The scope of Article 450 indicates that this article covers the installation of all transformers. There are ? exceptions that modify this Article 450 scope statement.

A

8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

why would Overcurrent protective devices on a transformer primary may require increased sizing?

A

due to the magnetizing inrush current.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Primary inrush current characteristics can vary by?

A

transformer design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What section of Article 450 details the basic ampere rating sizing requirements for overcurrent protection of transformers?

A

450.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The two tables of concern for transformer protection are ?

A

Table 450.3(A) for transformers over 1,000 volts, nominal and Table 450.3(B) for transformers 1,000 volts or less.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When increased sizing of the overcurrent protective device is utilized on the primary side of a transformer, overcurrent protection on the secondary side, sized closer to the load, is typically?

A

Required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When determining the overcurrent protection requirements for transformers in a circuit, other requirements from Article(s) ? may also need to be investigated.

A

230
240
408

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Table 450.3(A) provides provisions for both?

A

“any location” and “supervised locations only.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

For the purposes of the application of Table 450.3(A), a “supervised location” is a location where?

A

conditions of maintenance and supervision ensure that only qualified persons monitor and service the transformer installation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Study math for questions 12-22, lesson 4

A

Study math for questions 12-22, lesson 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A transformer supplying a fire pump is not permitted to have?

A

secondary overcurrent protection.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The transformer primary overcurrent protective device supplying a fire pump must be rated to carry the sum of the locked-rotor current of the fire and pressure pump motors plus ?

A

the full-load current of the accessory equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

For transformers covered by the scope of Article 450, the nameplate must provide which of the following that are vital information for calculating the available fault current on the transformer secondary?

A

-Impedance of transformers 25 kVA and larger
-kVA
-Primary and secondary voltage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NEC ? covers interrupting rating requirements for equipment.

A

110.9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

study questions 2, 8, 12- 20. lesson 5

A

study questions 2, 8, 12- 20. lesson 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A fully rated system is one in which all of the overcurrent protective devices have an individual interrupting rating at least as great as the ?

A

available fault current at their point of application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Only fully rated systems may be able to be?.

A

selectively coordinated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A series rated system consists of a ? that can be applied at a point in the system where the available fault current is greater than the interrupting rating of the load-side circuit breaker, but not greater than that of the main or line-side device.

A

circuit breaker and a circuit breaker

fuse and a circuit breaker

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

If a series-rated fuse/circuit breaker combination indicates a maximum 400-ampere Class J fuse is required?

A

any manufacturer’s fuse that is listed as UL Class J with 400 amperes or less can be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

There are many requirements and limitations for series rated systems, but only one advantage:

A

lower installed cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Series rated systems can cause problems or limitations with future ?

A

expansions, upgrades, or system integrity.

22
Q

The NEC defines ? as “localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the selection and installation of overcurrent protective devices and their ratings or settings for the full range of available overcurrents, from overload to the available fault current, and for the full range of overcurrent protective device opening times associated with those overcurrents.”

A

Coordination, Selective

23
Q

If a system is not selectively coordinated, unnecessary power loss can occur to loads that otherwise should be?

A

unaffected.

24
Q

The vertical axis of a time-current curve represents the ? .

A

time in seconds

25
Q

The horizontal axis of a time-current curve represents the ? .

A

current in amperes

26
Q

Both the ? and ? must be analyzed to determine if the circuit breakers are selectively coordinated.

A

unlatching time and clearing time

27
Q

For a fuse to selectively coordinate with an upstream fuse of a larger ampere rating,

A

the downstream fuse must clear before the upstream fuse melts.

28
Q

Fuses can be selectively coordinated for all levels of overcurrents by ?

A

following the fuse manufacturer’s selective coordination ratios.

29
Q

Circuit breakers with short-time delay and no instantaneous trip can be bought with an arc flash reduction maintenance switch which helps mitigate the

A

arc flash incident energy for occasions such as when an Electrical Worker must perform diagnostics on energized equipment.

30
Q

An emergency system overcurrent protective device is required to be selectively coordinated with all supply-side overcurrent protective devices per NEC Section ? .

A

700.32

31
Q

Selective coordination is an important consideration for reliability of ?

A

emergency systems to deliver power to vital loads.

32
Q

Selective coordination is required for?

A

multiple elevators supplied by the same source.

33
Q

study questions 15, 18 Lesson 6

A

study questions 15, 18 Lesson 6

34
Q

The NEC selective coordination requirements primarily are for systems or circuits in which the loads are vital for ? .

A

keeping continuous processing industrial plants operating

life safety

35
Q

Selective coordination is a benefit for any electrical distribution system and increases reliable power delivery to the loads. For most systems, it is a design consideration but.?

A

not mandatory.

36
Q

Study questions 1, 6-10, 19-21. Lesson 8

A

Study questions 1, 6-10, 19-21. Lesson 8

37
Q

For most circuits, phase OCPDs provide protection for all types of short-circuit conditions, including ?

A

ground faults.

38
Q

Lower-magnitude ground faults may be detected by the main OCPD but would not be cleared for a long period of time, during which ?

A

considerable damage could be incurred.

39
Q

Large ampere rated service-entrance overcurrent protective devices may not always sense and open ?

A

lower-level ground-fault conditions prior to extensive damage.

40
Q

The ? of ground-fault protection can depend not just upon the components, wiring, setting, and maintenance of the relay, but also upon the proper installation of the building wiring system.

A

reliability

41
Q

The two types of ground-fault sensing relays are ?

A

zero sequence and residual.

42
Q

The effective time-current curve for ground-fault protection consists of the ?

A

ground-fault relay and the phase overcurrent protective device.

43
Q

Residual ground-fault protection monitors ground fault currents in the ? .

A

grounding strap

44
Q

Zero sequence ground-fault protection monitors current in the ? .

A

neutral conductor

phase conductors

45
Q

Inappropriate GFPE settings are a common cause of?

A

main service nuisance power outages.

46
Q

Ground-fault protection can create selective coordination concerns depending upon?

A

the types and sizes of devices selected.

47
Q

The point where GFPE is most commonly required is at service disconnects of ?

A

1,000 amperes or more for 480/277-volt, 3-phase, 4-wire, solidly grounded wye electrical systems.

48
Q

For healthcare facilities, 517.17(B) requires the feeders to have ?

A

GFPE if the service has GFPE.

49
Q

The primary consideration for the protection of transformers is to accommodate the ? without sacrificing protection.

A

primary magnetizing inrush currents

50
Q
A