CSC CPD REVISION Flashcards

1
Q

The two Primary Strategic Objectives for Product Evaluation & Selection are …

A

“What is required.
What is available. “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 4 Methods for Water Penetration Control?

A

1 Mass

(Traditional, solid wall assemblies that shed most surface water & absorb the rest then release absorbed moisture as a vapour (Solid concrete, masonry and timber)

2 Barrier

3 Internal drainage plane

4 Rainscreen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Walls constructed as a moisture-management system incorporating :
cladding
air cavity
drainage plane
airtight support wall

to offer multiple moisture-shedding pathways, and diminish the forces attempting to drive moisture into the wall.

(Brick veneer cavity walls, furred-out clapboard walls and drainable EIFS walls. )

A

Rainscreen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Wall designed to shed all surface water with no moisture penetration ( EIFS, stucco, clapboard and curtain walls)

A

Barrier wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Air flows into the cavity behind the exterior cladding, equalizing the cavity pressure with the wind pressure, and thus minimizing the force (wind pressure) that causes most rain penetration.

A

Pressure-equalized rainscreens (PER)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A property of a material that opposes the passage of heat through it.

A

Thermal resistance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A measure of the effectiveness of the insulating material.
The larger the value, the better.

A

RSI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Principal function is to prevent:

Infiltration of outdoor air into a building
Exfiltration of indoor air to the outside

A

Air Barrier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A term describing a special class of materials that offer a high resistance to the flow of water vapour.

A

Vapour Barrier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 causes for Damp Walls ?

A

Air leakage through walls or roof construction to exterior.

Condensation on the wall surface or within the wall.

The presence of hygroscopic salts in cementitious materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A special building papers, membranes or coatings - used to separate an environment that is at a higher vapour pressure from an adjacent one at a lower vapour pressure.

A

Vapour retarders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Wall construction includes a drainage plane or moisture barrier located between the exterior cladding and the supporting wall that provides redundancy of moisture resistance.
(Stucco and clapboard walls)

A

Internal drainage plane

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The sum established by an owner as available for construction of a
project, including contingencies for cost increases during construction.

A

Construction budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A reliable cost/time evaluation of an item or project both in part and in total, both
present and life cycle. Estimate

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The sum established by an owner as available for an entire project including
such things as construction budget, professional fees, cost of land, rights of way, furnishings, equipment, financing and all other costs for a project.

A

Project budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A bill of quantities or a detailed listing and quantities of all items of material
and equipment necessary to construct a project.

A

Quantity survey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

WHO IS RESPONSIBLE FOR THE ESTIMATE?

A

The owner - the consultant - the estimator - the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Sometimes called “ballpark” estimates, they are based on historical costs related to a specific unit, ±20% accuracy

A

Order of Magnitude Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A method of estimate used when the schematic design drawings indicate the sizes and areas of the spaces and the overall facility, ±15% accuracy

A

ft2 or m2 and ft3 or m3 Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

These types of estimates are based on sizes of the spaces and the
systems and elements used for the building. Because systems are generally quite well
described this method can be as much as 100% accurate.

A

Systems Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

These types of estimates are prepared from detailed information
that is available from the working drawings, specifications and site visits. These estimates
are precise and generally provide a ± 5% accuracy rate.

A

Unit Price Estimates

22
Q

TYPES OF COSTS

A

1 Material Costs
2 Labour Costs
3 Equipment Costs
4 Contingencies

23
Q

A written document describing in summary form, the design parameters, functions, and elements intended to be used for a project which are identified during the initial stages of design.

A

Preliminary Project Description (PPD)

24
Q

An offer stating for what price the contractor will assume a contract.

A

Bid

25
Q

The specific and detailed form used to collect information about the bid.

A

Bid Form

26
Q

A document to make modifications to the bid documents during the bidding period

A

An Addendum (Addenda)

27
Q

Divided into sections A through G and Z

A

UniFormat

28
Q

Divided into Divisions 00 – 49.

A

MasterFormat

29
Q

The Drawings and the specifications have a ———— relationship similar to the
contract documents.

A

Complementary

30
Q

A project delivery method whose primary defining characteristic is a single multi-party contract signed by the owner, designer and builder, with financial incentives to enhance collaboration among the parties to the contract. - Conducive to fast-tracking.

A

Integrated Project Delivery

31
Q

A project delivery method whose primary defining characteristics are at least two separate and sequential contracts, first between owner and designer (consultant), then between owner and builder (contractor), with construction typically commencing only after design is substantially complete.

A

Design-Bid-Build

32
Q

A project delivery method where the design and construction (and perhaps commissioning) of a project are managed under a single entity.

A

Design-Build

33
Q

A law made by a provincial legislative assembly or by the federal government.

A

Act

34
Q

A proposed Act.

A

Bill

35
Q

A person or body charged with the responsibility for enforcement and administration of a code or regulation.

A

Authority Having Jurisdiction (per NBC)

36
Q

By developing these publications, organizations can help to ensure that products and
services are consistent, compatible, safe and effective.

A

Consensus standards

37
Q

These are threats, unwanted events, unforeseen conditions or other failure modes that
might occur during the project, such as:
 Accidents, fires and explosions.
 Serious equipment failure.
 Unforeseen geological conditions.
 Inadequate operating procedures, equipment or plant.
 Significant design inadequacies.

A

Hazards

38
Q

An oral or written agreement between two or more parties that is enforceable by law. In order to be valid, a contract requires an offer, an acceptance of that offer and, in common-law jurisdictions, consideration.

A

Contract

39
Q

It is the most important field of tort law as it rules most activities of modern society.

A

Negligence

40
Q

Professionals must exercise a ————— that is considered the same as the “average”
professional in that profession.

A

Standard of care

41
Q

A professional must exercise a —————- not only to the parties involved with a project but
also to innocent bystanders and the public.

A

Duty of care

42
Q

They shall be responsible for establishing, initiating, maintaining, and supervising all health and safety precautions

A

Contractor

43
Q

They will investigate the impact on the Work of the discoveries of artifacts and fossils.

A

Consultant

44
Q

Responsible to provide evidence of compliance with workers’ compensation

A

Contract

45
Q

Will be responsible to interpret the requirements of the Contract Documents.

A

Consultant

46
Q

Will prepare Change Orders and Change Directives

A

Consultant

47
Q

Shall furnish promptly to the Consultant two copies of certificates and inspection reports relating to the Work.

A

Contractor

48
Q

Shall have control and management of the Place of the Work with respect to existing conditions.

A

Owner

49
Q

What are the 2 types of owners?

A

Public Sector & Private Sector

50
Q

A term Refers to materials that are reclaimed from products that have already
served their intended end-use as a consumer item.

A

Post-Consumer

51
Q

A term that refers to water-efficient choices in planting and irrigation design.

A

Xeriscaping