Name the the main members of the project team.
Owner, Contractor, Consultant
Who is responsible for: Purchases and maintains liability insurance, and furnishes performance and payment bonds?
Contractor
Who is responsible for: Installs, maintains and supervises safety?
Contractor
Who is responsible for: Represents the owner?
Consultant
Who is responsible for: Observes the project, and determines the progress and quality of the work through site reviews.
Consultant
Who is responsible for: submits itemized application for payment
Contractor
Who is responsible for: recommends amounts due and certifies payment.
Consultant
Who is responsible for: interprets construction documents
Consultant
Who is responsible for: reviews work verifies compliance
Consultant
Purchases and maintains liability insurance?
Contractor 1.1.1.1
Who does the owner expect to be fair when pricing changes in the work?
Contractor
A budget is how much money is available to spend? T or F
True
Describe the difference between a project budget and a construction budget:
CB. = sum available for construction
PB = entire project incl CB land costs professional fees include legal right of way etc..
List the four principal methods for estimating project costs:
Order of magnitude, square foot/ meter cubic foot meter, system estimates, unit price estimates.
The construction phase is when the method of project delivery is determined? T or F
False
The commissioning phase begins when?
Early in the construction process.
The construction phase is when project systems and assemblies are tested to ensure they meet design intent?
Operations phase
Why addendum should not be issued to close to the bid closing date?
Enough time to respond.
Where should the conditions for disqualification of the bidder be included?
Instructions to bidders.
What type of information should be included in the instructions to bidders?
Where call bids, method for bids, address or email; time / date; other instructions; conditions affecting award of contract; bid security requirements; cobtractvexec req
Define the project manual?
Written / bound document information for bidding and negotiation + constructing and completing the project. Not the drawings.
The general conditions of a contract define the administrative, temporary and procedural req of a project.
False. The answer is general requirements. GC is from CCDC (defines relationships, rights and responsibilities)
The relationship between spec and drawings is ?
Complementary
What is a spec
Written description of materials and methods.
Master Format is divided into what 5 subcategories?
1 general req; 2 facility construction; facility services; site and infrastructure; process equipment.
Master format is used to define the scope of work of trades
False
Explain the difference between a prescriptive and performance spec
Pre recipe Finnish work
Perform detailed result
Referencing a performance standard is a good way to ensure high quality products
False, not all standards are good
What is the main reason for using a proprietary spec
Control product selection, ensure exact results
How is a consensus standard incorporated into a spec
Reference to a number, title and other designation
Explain why it is important to date when referencing a consensus standard
Allows the contractor to determine what design conditions were in force when the project manual was issued. Unfair not to.
What preferred grammatical mood for structuring specification sentences
Imperative
When writing a number less than one in a specification, a zero hound be placed to the left of the decimal point
True
Explain why “Consultant” might be capitalized in the project manual?
Defined terms in GC
Explain why the recommendations for language and style are important
Accuracy, brevity and clarity - easy to understand
Describe the process a specification writer should use if he or she wants to reuse an old specification section for a new project.
Research and check details, make sure the section is written correctly and coordinated with other parts.
Explain why a master specification needs to be edited before it can be used in a project.
Lots of choices; materials, methods and practices. To meet the projects requirements you need to delete unnecessary info, only relevant information is included.