Critical Path Analysis Flashcards

1
Q

What does a precedence or dependence table show?

A

Which activities must be completed before others are started

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 3 main characteristics of a dummy activity?

A
  • takes no time
  • doesn’t cost anything
  • purpose is to show dependencies between activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the weights of activities representing?

A

The duration of such activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a critical activity?

A

If an increase in said activity leads to an overall increase in the duration of the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a critical path?

A

The longest path contained in the network - made entirely of critical activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where does EET = LET?

A

At a node on the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the float of an activity?

A

The amount of time it can be delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the formula of total float?

A

LFT - Duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the float of a critical activity?

A

0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a gantt (cascade) chart?

A

A graphical way to represent the range of possible start and finish times for all activities on a single diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly