Critical path analysis Flashcards
1
Q
What does a precedence table show?
A
Which activities in a task must be completed before others can be started.
2
Q
What is the float of an activity?
A
The amount by which the difference between the earliest start and latest finish time exceeds the activity duration (extra possible time).
3
Q
What is a critical activity?
A
An activity with no float.
-if a critical activity is delayed, the project completion time will also be delayed.
4
Q
What is a critical path?
A
The path through a network between critical activities.
5
Q
What is the latest finish time of all ending activities?
A
MUST BE THE SAME
this is the minimum project completion time.