Critical path analysis Flashcards

1
Q

What does a precedence table show?

A

Which activities in a task must be completed before others can be started.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the float of an activity?

A

The amount by which the difference between the earliest start and latest finish time exceeds the activity duration (extra possible time).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a critical activity?

A

An activity with no float.

-if a critical activity is delayed, the project completion time will also be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a critical path?

A

The path through a network between critical activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the latest finish time of all ending activities?

A

MUST BE THE SAME

this is the minimum project completion time.