Critical Path Analysis Flashcards

1
Q

The first node is called..

A

The source node.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The last node is called..

A

The sink node.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Early time events are calculated by..

A

A forward scan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Late time events are calculated by..

A

A backward scan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Total Float

A

The amount of time that an activity’s start may be delayed without affecting the duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

critical activity

A

These will have equal numbers in their early event times and late event times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

total float

A

total float = latest finish time - duration - earliest start time (bottom number after activity - the number on the arc - the top number before the arc starts)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

total float of a critical activity

A

This will always be zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

how to plot gannt chart

A

plot first early event time as start of gannt box, then add path length to start of gannt box for clear bit of box. then plot last late event time. the distance between clear box and late event time is the shaded box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly