Critical Path Analysis Flashcards
What does the middle box mean
The duration
What does the first box mean
The earliest time an activity can start
What does the last box
Latest time an activity can finish without delaying the project completion
What do u use a forward pass for
The earliest start time for each activity and the minimum completion time
When on a forward pass and in between two boxes how do u pick
Largest time
When doing a backwards pass
You take away the middle box from the last box and put that in the next node
When picking between 2 pick the lowest
What is a float time
Where an activity can have a range of start times and still be able to meet the minimum requirement
What is a critical activity
Has no float time
How to find the float time
Last box - (the other 2 boxes)
What is a critical path
A path of only critical activities