critical path analysis Flashcards

1
Q

how are activity networks presented?

A
  • acrs represent activities
  • arc weights show the durations of the activities
  • verticies represent events (moments between the completion of an activity and the start of another
  • single start event (source) and single finish events (sink)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

why are dummy activities needed?

A
  • allows arcs to be uniquely labelled using the events at its ends
  • establishing priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are the components of dummy activities?

A
  • drawn with dashed lines
  • have a 0 duration

try to use as less as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Draw the activity network

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the minimum project completion time?

A

the time in which a project can be completed, assuming there are no unexpected delays
* length of the longest path in the directed activity network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is a critcal acitivity?

A

an activity on the longest path
* between two critcal events
* difference between the two critcal events is the activity duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the rules when completing the forward pass (earliest times) ?

first box

A
  • choose the largest out of two possibilities (two paths incoming to a node )
  • earliest time for the start event is 0
  • earliest time to finsih is the minimum project completion time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the rules when completing a backwards pass (latest event time) ?

A
  • choose the smallest out of two possibilities (two paths leaving a node )
  • latest event time for the finish event is the project completion time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is the critical path?

A

series of critical activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is a float?

total float

A

the amount of time by which the duration of the activity can be extended without having any effect on the minimum project completion time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is an independent float and interfering float?

A
  • independent float: unique to the activity
  • interfering float: impacts the floats of the other activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are the formula’s for the floats?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which activities are the critical activities?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

how are cascade diagrams usually drawn?

A

time is boxes horizontally and letters are put vertically
put duration as a filled box and float in a dashed line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
16
Q
A
17
Q
A
18
Q
A
19
Q
A
20
Q
A