Critical Path Analysis Flashcards

1
Q

Float meaning

A

Amount of time the early start of an activity it can b delayed w/o delaying the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Total float calculation

A

Max time of destination point - min time of starting point - duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Independent float calculation

A

Min destination point time - max starting point time - duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Interfering float calculation

A

Total float - independent float