Critical Path Analysis Flashcards

1
Q

Free Float

A

EST start of next task – EST start of this task – duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Total Float

A

LFT of activity – EST of activity – duration