Critical path analysis Flashcards
1
Q
CPA analysis
A
Planning method that allows a project to be completed in the shortest time possible
2
Q
Float
A
The duration an activity can be delayed without the overall project being delayed further.
Float= LFT - duration - EST
3
Q
Critical path
A
Activities with no float, which means they cannot be delayed without delaying the whole project
4
Q
Pros
A
Helps business plan ahead
Helps with complex and time sensitive projects
Useful for risky projects
5
Q
Cons
A
Largely based on estimates and assumptions
Does not guarantee the success of a project
Too many activities make the network diagram too complicated