Critical Path Analysis Flashcards
Precedence Table
Has the activities listed in the left column and their dependencies on the right.
- Put a - where there are no dependencies
- If an activity is dependent on an activity that depends on others only put the one it is directly dependent on
Creating an activity network
Start with a node labelled 0
Point arcs representing activities that aren’t dependent on any others from there
Label each node with an increasing number. connect multiple arcs where one is dependent on multiple
Connect the terminating activity/activities to a sink node at the end
Arcs must be straight
Dummy Arcs
Dotted lines from a node to another to show that the activity that is dependent on is needed for the one on the other end of the dummy
When do you need a dummy arc?
- Where two activities at the same node are needed, draw one to a separate node and add the dummy
- If an activity is needed for one activity on its own and another activity has that and another one needed, draw a dummy from the node where only it is needed
Early event time
The earliest time a project can be started based on all events it is dependent on being completed
Late event time
The latest time a project can be started without extending the time needed for a project
Finding early and late event times
Trace forward from the source node for early, the latest time a needed event is completed
Trace back from the sink for the late, the earliest time from this
Critical activity
Any increase in its duration will increase the duration of the whole project
Early start time = late start time where the values on the next node are equal to the values on that node plus the length of the activity
Critical path
A path from the source node to the sink node that exclusively follows critical activities
Float of an activity
The amount of time that its start may be delayed without affecting the duration of the project
Float of an activity formula
latest finish time - duration - earliest start time
Gantt Diagram
Shows the time each activity can be completed in visually using a diagram with rectangles for each activity
Critical activities Gantt diagram
Rectangles across one line for all of them connected
Non-critical activities Gantt diagram
Draw a rectangle from the early start time with length the duration. Draw a dotted rectangle from there to the late time.
Each should have a new line
When an activity must be at a time Gantt diagrams
No matter how far through the float it is shifted the rectangle will always encompass that time