Craftsman Flashcards
Margin Symbol R
Requiring verification/inspection as defined by RADCON
Margin Symbol S
FMA procedure requiring verification by a members of Ships Force
Margin Symbol C
Cleanliness Inspection by craftsman
Margin Symbol I
QAI or NDT Inspection
Margin Symbol CI
Independent Cleanliness Inspection by SCI/RCI
Margin Symbol Q
Critical Quality Control Points (Q-Points)
Margin Symbol V
Craftsman Verification
Margin Symbol G
Government Notification Required
What are Q-Points
Critical Execution Points whose proper accomplishment overwhelmingly affect the ultimate FIRST - TIME QUALITY SUCCESS
3 types of Technical Work Documents
- MP
- FWP
- CWP
Purpose of TWD
Provides the craftsman with clear, concise, technically correct instructions
What needs OQE?
- SUBSAFE
- Level 1
- Nuclear
- Weight Testing
Pen and Ink changes to a FWP will be made with the approval of who?
LPO/LWC Supervisor or Division Officer
Pen and Ink changes to a CWP will be made with the approval of who?
QAO, Quality Assurance Supervisor (QAS) or QAI
How do you do a pen and ink change?
Draw a single line the portion of procedure to be changed, and enter change adjacent to that portion. Initial, date and print name of the approving authority for change.
Technical Pen and Ink changes are approved by who?
Department Head