CPD Questions Flashcards

1
Q

What does the JCT D&B say about safety?

A
  • That all works shall be undertaken in line with all relevant health and safety laws
  • Supplementary Provision 2
  • Non-compliance is grounds for termination.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What common JCT D&B amendments are there?

A
  • DLP from 6 months to 12 months
  • Puts full responsibility on to Contractor for verifying the ER’s. Otherwise, errors and ambiguities are Employer’s responsibility.
  • Risk of adequacy of Employer’s design usually transferred to Contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does JCT say about BIM?

A
  • Compliance with ERs

- Supplemental Provision regarding BIM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What bonds can be used in JCT2106?

A
  • Advance payment Bond
  • Retention Bond
  • Performance Bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What bonds are there under NEC?

A
  • Performance Bond X13
  • Advance Payment Bond (Advance Payment to Contractor) X14
  • Retention Bond now optional under X16
  • (also PCG)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What can the EA not do under JCT?

A
  • Give possession of the site
  • Make payments
  • Deduct damages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you tell me some of the important JCT D&B clauses?

A
  • Complete the Works in a proper and workmanlike manner
  • Proceed regularly and diligently
  • Relevant Events and Matters
  • Partial Possession
  • Discrepancies and Divergences
  • Adequacy of design - often amended to transfer complete design liability to Contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Are you aware of any cases relating to adequacy of design?

A
  • Henry Boot vs. Co-Operative Insurance

- Judge found Boot responsible for taking outline design and making it work in the detail phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Loss and Expense in JCT and how is it dealt with?

A
  • Loss and Expense incurred by Contractor due to being materially prevented in their works by Employer.
  • Notify employer ASAP and continue to update if the L&E continues
  • Employer ascertains amount due and notifies contractor after each update
  • Contractor paid through normal payment mechanisms
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the payment process in JCTDB16?

A
  • Interim Application to be made before interim valuation 7 days before due date
  • Due date
  • (Interim Certificate) Payment notice 5 days after due date (by law)
  • 14 days to final date for payment
  • No less than 7 days prior to FDP a pay less notice can be issued
  • Only the Due Date 5 day period is held in statute
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the last formal CPD you did? Why was it formal?

A

CSCS Managers and Professionals Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the last informal CPD you did?

A

Q&A session with steelwork manufacturer about castellated vs. normal beams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly