CPA Flashcards

1
Q

State two advantages of CPA:

A

1: Helps to reduce risks and costs of complex projects 2: helps to make decisions and a plan at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

State two disadvantages of CPA:

A

1: Reliability of CPA largely based on accurate estimations and assumptions made
2: Resources may not be as flexible as hoped by management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you calculate: Float

A

LFT - Duration - EST = FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define CPA:

A

This is a method of organising the activities in a project to find the most efficient method of completing a project, without wasting resources. (TIME, MONEY, MATERIALS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is EST?

A

Earliest Start Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does EST do?

A

This shows the earliest time an activity can be started. It is dependent on the previous activity being completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is LFT?

A

Latest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does LFT do?

A

LFT is the latest possible time for a task to finish avoiding delays in the project. Any delay in tasks will hold up the project and the completion will be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are four common errors in CPA network construction?

A
  • The diagram must start and end with a node.
  • The connecting arrows must show an activity (and times)
  • The arrows must never cross over.
  • You must never enter an end node until you know what comes next and whether there are more simultaneous tasks.