Cost Variance Flashcards

0
Q

Cost Performance Index (CPI)?

A

CPI= EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Cost Variance (CV)?

A

CV= EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Variance (SV)?

A

SV= EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Performance Index (SPI)?

A

SPI= EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate To Completion (ETC)

A

ETC= EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Earned Value (EV)

A

Value if the work completed to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Present Value (PV)

A

Today’s value of future cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC?

A

Budget forecast that takes project variance into account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate At Completion- ETC

A

Estimate To Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned value

A

Budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PERT

A

Est duration= (optimistic +4most likely+ pessimistic)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Channels of communication

A

n=number of people nx(n-1)/2
n=10
10x(10-1)/2=45

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Variance Allowance

A

Measures project variance against scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

AC

A

Actual cost what u have spent to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Standard Deviation

A

Pessimistic(18) - Optimistic (6)
Over 6 P-O/6 as fraction
18-6/6= 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly