Cost Variance Flashcards
Cost Performance Index (CPI)?
CPI= EV/AC
Cost Variance (CV)?
CV= EV-AC
Schedule Variance (SV)?
SV= EV-PV
Schedule Performance Index (SPI)?
SPI= EV/PV
Estimate To Completion (ETC)
ETC= EAC-AC
Earned Value (EV)
Value if the work completed to date
Present Value (PV)
Today’s value of future cash flow
EAC?
Budget forecast that takes project variance into account
Estimate At Completion- ETC
Estimate To Completion
Planned value
Budget assigned to scheduled work
PERT
Est duration= (optimistic +4most likely+ pessimistic)/6
Channels of communication
n=number of people nx(n-1)/2
n=10
10x(10-1)/2=45
Variance Allowance
Measures project variance against scope baseline
AC
Actual cost what u have spent to date
Standard Deviation
Pessimistic(18) - Optimistic (6)
Over 6 P-O/6 as fraction
18-6/6= 2