Cost Planning Flashcards

1
Q

What is Cost Planning?

A

Is an attempt to introduce more rigour and accuracy into the pre-contract costing process. The cost planning process commences with the preparation of an approximate estimate by the QS, and then the setting of cost targets, which are based upon elements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an Element?

A

Part of a building that fulfils a specific function or functions irrespective of its design, specification or construction i.e External Walls.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are cost targets?

A

Cost targets are based upon elements. As the design evolves these cost targets are checked for any under-or-overspending against the Architects details.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Stage 0 of the RIBA plan of Work Stages

A

Strategic Definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the process of financial advice given at Stage 0 by the QS?

A

Order of Cost Estimate - to establish affordability of a proposed development
Cost Range - Financial limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Stage 1 of the RIBA plan of Work Stages

A

Preparation and Brief

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the process of financial advice given at Stage 1 by the QS

A

First Stage Estimate - Preliminary Estimate - single rate estimating - Lump Sum based on GIFA/GFA
Feasibility Study - cash flow predictions (i.e. s-curve)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is stage 2 of the RIBA plan of Work Stages?

A

Concept Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the process of financial advice given at Stage 2 by the QS?

A

Cost Plan 1/2 - elemental cost analysis
Single rate estimating
Cost Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is stage 3 of the RIBA plan of Work Stages?

A

Spatial Coordination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the process of financial advice given at Stage 3 by the QS?

A

Cost Plan 3 - elemental cost analysis
Approximate Quantities
Cost Planning
Pre-tender estimate established (Confidential)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is stage 4 of the RIBA plan of Work Stages?

A

Technical Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the process of financial advice given at Stage 4 by the QS?

A

Cost Control and cost checking
Bill of Quantities produced, tender process
Compare the returned tender figure against the pre-tender estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is stage 5 of the RIBA plan of Work Stages?

A

Manufacturing & Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the process of financial advice given at Stage 5 by the QS?

A

Cost Control/analysis and cost checking (variations etc.)

Financial Statements to the Client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the floor area or m2 method?

A

The superficial method is a single price rate method based on the cost per metre of the building. This method is restricted to the early stages of design - approximate estimating

17
Q

What is the functional unit method?

A

The unit method is a single price rate method based on the cost per functional unit of the building, a functional unit being, for example, a hotel bedroom.

18
Q

What is the Elemental method?

A

The elemental method requires the calculation of element unit quantities (EUQs) and element unit rates (EURs) using the detailed rules of measurement contained in the NRM1.

19
Q

What is approximate quantities?

A

This is regarding as the most reliable and accurate method of estimating, provided that there is sufficient information to work on. Think stage 3 of RIBA plan of work stages. The quantities can be based on composite rates built up from data available in the office.

20
Q

Example of a composite item in a cost plan:

A

Excavate trench width exceeding 0.30m, maximum depth 1.00m; filling to excavations, disposal of excavated material off site, in situ concrete (20N/mm2 aggregate) foundation poured against the earth, 275mm cavity brickwork to 150mm above ground level, bitumen-based dpc, facings externally (everything grouped to-gether if measured in NRM2 items would be seperate)