Cost Management Flashcards

1
Q

Plan Cost Management

A

Inputs:

  • project charter
  • PMP
  • OPAs, EEFs

Tools & Techniques:

  • expert judgement
  • data analysis
  • Meetings

Outputs:
- Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimate Costs

A

Inputs:

  • PMP
  • Project documents
  • OPAs, EEFs

Tools & Techniques:

  • expert judgement
  • analogous estimating
  • parametric estimating
  • bottom-up estimating
  • three-point estimating
  • data analysis
  • PMIS
  • Decision making

Outputs:

  • cost estimates
  • basis of estimates
  • project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Determine Budget

A

Inputs:

  • PMP
  • project documents
  • business documents
  • agreements
  • OPAs, EEFs

Tools & Techniques:

  • expert judgement
  • cost aggregation
  • data analysis
  • historical info review
  • funding limit reconciliation
  • financing

Outputs:
- cost baseline
- project funding requirements
project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Controls Costs

A

Inputs:

  • PMP
  • project documents
  • project funding requirements
  • work performance data
  • OPAs

Tools & Techniques:

  • expert judgement
  • data analysis
  • to-complete performance index
  • PMIS

Outputs:

  • work performance info
  • cost forecasts
  • change requests
  • PMP updates
  • project document updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly