Cost management Flashcards

1
Q

3 types of estimating

A

1 - Historical 2 - Bottom-up 3 Parametric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 important principles of money management

A

1 - Budgeting 2 - Invoicing 3 - Tax

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

2 types of costing

A

1 - Direct 2 - Indirect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define direct costs

A

Direct costs are costs that can be directly attributed to a specific project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

3 example of direct costs

A

1 - Labour
2 -Raw materials
3 - Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

3 example of indirect costs

A

1 - General administration
2 - Rental
3 - Utility costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define indirect costs

A

Indirect costs are costs that cannot be directly attributed to a specific project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Debit / Credit framework formula

A
A = L + SE
(Assets = Liabilities + Stakeholders Equity)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

BCWS

A

Budget Cost Work Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Formula

Planned value

A

PV = planned % complete X BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Formula

Cost variance (CV)

A

CV = EV - AC

Cost variance = Earned value - Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

ACWP

A

Actual Cost Work Performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which formula to calculate if project is on schedule or not?

A

CV = EV - AC

Earned Value = Lower) - (AC = higher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How to determine if project is on budget?

A

1 - Calculate time spent by max time allowed
2 - Compare the calculated variable with cost spent
3 - Determine if project is behind or ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a simplified explanation of Earned Value (EV) in a project

A

An unexpected cost that occurs that was not mentioned in the original cope of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Formula

Crashing formula

A

(Crash cost - Normal cost) / Crash periods available

17
Q

Which path must be chosen when compressing

A

The path with the least cost to crash