Cost Management Flashcards
Life Cycle Costing
Looks at entire life of product (including maintenance)
Value Analysis
aka Value Engineering
finds least costly way to do the same work (decrease cost while maintaining scope)
Inputs: Plan Cost Management
- PM Plan
- Project Charter
- EEFs
- OPAs
Outputs: Plan Cost Management
Cost Management Plan
Inputs: Estimate Costs
- PM Plan
- Project docs
- Project Schedule
- Risk Register
- Lessons Learned Register
- Resource Requirements
- EEFs
- OPAs
Outputs: Estimate Costs
- Cost Estimates
- Basis of Estimates
- Project docs updates
Basis of Estimates
doucuments how the estimates were developed and their ranges, including assumptions made and constraints impacting the estimate
Components of Cost Management Plan
- levels of accuracy and precision needed for estimates
- approved estimating techniques
- reporting formats
- rules for measuring cost performance
- guidance re: documenting costs & inclusion of directs & indirect costs
- control thresholds
- change control procedures
- information on control accounts, and monitoring spending
Estimate Ranges
Rough Order of Magnitude Estimate
Budget Estimate
Definitive Estimate
Rough Order of Magnitude Estimate
made during project initiating, range is typically -25 to +75 percent
Budget Estimate
made during planning, range of -10 to +25 percent
Definitive Estimate
refined through planning process, typically with a range of -5 to +10%
Inputs: Determine Budget
- PM Plan
- Project docs
- activity cost estimates
- basis of estimates
- project schedule
- risk register
- Business documents (including business case and benefits mgmt plan)
- Agreements
- EEFs
- OPAs
Outputs: Determine Budget
- Cost baseline
- Project funding requirements
- Project docs updates
Project Funding Requirements
state how and when the project will be funded