Cost Management Flashcards

1
Q

Life Cycle Costing

A

Looks at entire life of product (including maintenance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Value Analysis

A

aka Value Engineering

finds least costly way to do the same work (decrease cost while maintaining scope)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Inputs: Plan Cost Management

A
  • PM Plan
  • Project Charter
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Outputs: Plan Cost Management

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Inputs: Estimate Costs

A
  • PM Plan
  • Project docs
    • Project Schedule
    • Risk Register
    • Lessons Learned Register
    • Resource Requirements
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Outputs: Estimate Costs

A
  • Cost Estimates
  • Basis of Estimates
  • Project docs updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Basis of Estimates

A

doucuments how the estimates were developed and their ranges, including assumptions made and constraints impacting the estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Components of Cost Management Plan

A
  • levels of accuracy and precision needed for estimates
  • approved estimating techniques
  • reporting formats
  • rules for measuring cost performance
  • guidance re: documenting costs & inclusion of directs & indirect costs
  • control thresholds
  • change control procedures
  • information on control accounts, and monitoring spending
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate Ranges

A

Rough Order of Magnitude Estimate

Budget Estimate

Definitive Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Rough Order of Magnitude Estimate

A

made during project initiating, range is typically -25 to +75 percent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Budget Estimate

A

made during planning, range of -10 to +25 percent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Definitive Estimate

A

refined through planning process, typically with a range of -5 to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Inputs: Determine Budget

A
  • PM Plan
  • Project docs
    • activity cost estimates
    • basis of estimates
    • project schedule
    • risk register
  • Business documents (including business case and benefits mgmt plan)
  • Agreements
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Outputs: Determine Budget

A
  • Cost baseline
  • Project funding requirements
  • Project docs updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Funding Requirements

A

state how and when the project will be funded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Difference between cost baseline and cost budget

A

Cost Baseline: costs + cotntingency reserves

Cost Budget: Cost baseline + management reserves

17
Q

Cost aggregation

A

first step in creating budget. activity costs are rolled up into work package costs, then work package costs to control account estimates, then control account estimates to project estimates.

18
Q

Steps in Determine Budget

A
  1. cost aggregation
  2. check cash flows to determine schedule impacts
  3. reconcile with cost constraints in charter
19
Q

Inputs: Control Costs

A
20
Q

Cost Baseline

A

costs to produce all of the deliverables in the project, plust contingency reserves

S-curve accounts for timing with funding

21
Q

Reserve Analysis

A

part of Control Costs process to determine if contingency reserves are still appropriate (may be increased due to new risks, or reduced due to contemplated risks on completed activities that did not occur)

reminder: any changes require a change request

22
Q

What does the occurance of many unknown risks suggest?

A

Risk management efforts in planning were inadequate and need to be redone.

23
Q

Use of Management Reserves

A

applied to unknown risks

requires a change request to move funds to cost baseline

24
Q

Outputs: Control Costs

A
  • Work performance information
  • Cost forecasts
  • Change requests
  • PM Plan updates
  • Project docs updates
  • OPAs updates
25
Q

Cost Forecast

A

Forecast of how much project could cost in the end – based on rate of spending now.

Calculated using Estimate at Completion

26
Q

Earned Value Analysis

A

measures project performance against scope, schedule, and cost baselines

27
Q
A