Cost Equations Flashcards
BAC
Budgeted Actual Cost
PV
Planned Value
PV = Planned % complete x BAC
EV
Earned Value
Actual % x BAC
AC
Actual Cost
Sum of the cost for the given period
CV
Cost Variance
CV = EV - AC
Cost variance = Earned Value - Actual Value
Positive is under budget, negative if over budget
CPI
Cost Performance Index
CPI = EV / AC CPI = Earned value / actual cost
> 1.0 is below budget
< 1.0 is above budget
SV
Schedule Variance
SV = EV - PV
SV = Earned Value - Planned Value
Positive is ahead of schedule
Negative is behind schedule
SPI
Schedule Performance Index
SPI = EV / PV SPI = Earned value / planned value
> 1.0 is ahead of schedule
< 1.0 is behind schedule
EAC
Estimate at Completion
EAC = BAC / CPI
ETC
Estimate to Completion
ETC = EAC - AC
VAC
Variance at Completion
VAC = BAC - EAC
TCPI
To Complete Performance Index
TCPI = (BAC - EV) / (EAC - AC)
TCPI = (BAC - EV) / ETC
EMV
Expected Monetary Value
EMV = Probability x Impact