Cost Equations Flashcards

1
Q

BAC

A

Budgeted Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

Planned Value

PV = Planned % complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV

A

Earned Value

Actual % x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC

A

Actual Cost

Sum of the cost for the given period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance

CV = EV - AC
Cost variance = Earned Value - Actual Value
Positive is under budget, negative if over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

Cost Performance Index

CPI = EV / AC
CPI = Earned value / actual cost

> 1.0 is below budget
< 1.0 is above budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

Schedule Variance
SV = EV - PV
SV = Earned Value - Planned Value

Positive is ahead of schedule
Negative is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

Schedule Performance Index

SPI = EV / PV
SPI = Earned value / planned value

> 1.0 is ahead of schedule
< 1.0 is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

Estimate at Completion

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC

A

Estimate to Completion

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

A

Variance at Completion

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To Complete Performance Index
TCPI = (BAC - EV) / (EAC - AC)
TCPI = (BAC - EV) / ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EMV

A

Expected Monetary Value

EMV = Probability x Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly