Contract Practice Flashcards

Understanding concepts of JCT contracts, forming contracts, contents of contracts and contractual mechanisms.

1
Q

What are the 5 key things needed to form a contract?

A

Offer, acceptance, consideration, capacity, intention and legality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are Contract Particulars?

A

Aspects of the Contract that are bespoke to the project i.e completion date, date of possession, defects rectification period and LD’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Recitals under a JCT contract?

A

They set and overview of the project, including brief description of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Articles under a JCT contract?

A

Identify primary obligations of the parties under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Attestation?

A

Process of confirmation, under seal and under hand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an LOI?

A

Indicates one parties intention to enter into a formal contract with another, typically asking for works to start before formal contract is executed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What info is typically in an LOI?

A

-Detailed description of works
-Contract Sun (if it is agreed)
-Date of possession
-Date for completion
-Insurances
-Method of payment
-Employers right to not enter main contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a PCSA?

A

Pre-Construction Services Agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are typical PCSA services?

A

-Contribution to design
-Advice on buildability, sequencing and risk
-Advise on selection of subbies
-Help develop cost plan and programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly