Contract Practice Flashcards
What is Indemnity?
Indemnity is the obligation that one party holds in paying compensation to another party that suffered losses.
What is insurance?
transferring a risk from one party to another in exchange for a payment made.
What is the difference between Indemnity and Insurance?
Insurance can be seen as a periodic payment that is made to guard against any losses suffered, whilst indemnity is a contract between two parties for which the injured party will receive compensation for any losses.
How would you assess the cost of LDs a client proposes?
- Check LD figure is a genuine pre-estimate of the loss
- Explain even if LDs are applied, client may need to substantiate the figure
- Cannot be punitive or figure may not be enforceable
- If LDs not enforgeable employer would have to pursue the maic Co for actual direct loss that can be susbtantiated through formal dispute resoln procedure
What are EOT?
EOT adjust the completion date and relieve the contractor’s liability to pay liquidated damages for the period of the extension
What are liquidated damages?
a genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met
What must be in place for LDs to be claimed?
- A non-completion certificate
- had a certificate been issued, a witholding notice (pay less notice)
What if E actually suffered no loss of damage?
- it does not matter
- damaged will be deducted at the pre-agreed rate stated in the contract
What are the benefits of being able to grant an EOT?
- relieves Co liability for LD for the delay they did not cause
- enables another completion date to be set, maintianing the Es ability to deduct LDs if another delay occurs
- prevents time becoming at large
what happens when time is at large?
- no completion date set
- Co only has obligation to complete the works in a reasonable time
- LDs cannot be claimed as no date to take them from
- E would have to prove Co did not complete in a reasonable time
What are relevant events in the JCT contract?
the events that entitle the contractor to an EOT
p178
What is retention?
Retention is a sum of money (the retention fund) held by the employer as safeguard against defective or nonconforming
work or materials provided by the contractor. It is to safeguard the employer against defects discovered after PC (latent) or the contractors failure to complete the C
What is a prime cost sum ?
a sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g. ceramic wall tiles at £36.00/m or door
furniture at 75.00/door).It is a supply-only rate for
materials or goods where the precise quality of those materials and goods are unknown. It excludes design and install costs, OHP and prelims.
What is a Provisional Sum?
A sum of money included in pricing doc. A provisional sum is provided to cover the cost of something that cannot be entirely
foreseen or detailed accurately at the time tenders are
invited e.g. ceiling grid amendment and tile replacement where needed in the data halls