Contract - Performance Case Law Flashcards

1
Q

Cutter v Powell (1795)

A
  • Contract to crew the ship was an entire agreement.
  • Wages only payable on completion (condition precedent).
  • Widow not entitled to a quantum meruit claim.

Key Point: Contract was deemed indivisible. Hard case that after the courts developed various mechanisms to avoid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Richie v Atkinson (1808)

A
  • Cargo contract deemed divisible when contracted tonnage was not provided.
  • It was possible to divide the contract and pay for what had been delivered.
  • D entitled to damages for tonnage missing.

Key Point: Past performance is independent from future obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bolton v Mahadeva [1972] CA

A
  • central heating installation did not function. Mahadeva refused to pay and Bolton refused to rectify.
  • At first instance it was ruled contract valid and payment due.
  • In CA contract discharged as no substantial performance of contract.

Key Point: Substantial performance only applies where there are minor incomplete work values.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Hoenig v Issacs [1952] CA

A
  • Defects in interior decoration contract.
  • Work ruled as substantial performance therefore contract price less cost of remedy awarded.

Key Point: Contrasts to Bolton v Mahadeva. No bright line on what is determined substantial performance. Approved in Williams v Roffey [1991].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Dakin v Lee [1916] CA

A
  • Defective repairs to the house of Lee.
  • Ruled the contract price less cost of repairs was due. Substantial performance upheld.

Key Point: Mitigates harshness of entire agreements (condition precedent). Generally applied in cases except those involving Sale of Goods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sumpter v Hedges [1898]

A
  • Builder was unable to finish works started. Home owner took over and finished the work.
  • Builder could not claim partial performance (therefore claim for works completed) as the home owner had no choice but to accept the works completed thus far.
  • Payment for materials left onsite was allowed.
  • In order to be validated for labour costs, an inference of a fresh contract to pay must be proven.

Key Point: Partial performance requires active acceptance by the injured party. If not accepted, the party in breach must prove incontrovertible benefit for a restitution claim or a fresh contract. Links to property rights (whatever is joined to the land becomes part of the land).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Moore v Landauer [1921] CA

A
  • Fruit was packed in 24 tins not 30 as per the contract. No difference in commercial value.
  • CA held that the good could be rejected since the description of the goods was not met.

Key Point: Hard case. Invocation of the SOG Act despite obvious delivery of commercially equal goods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Arcos v Ronaasen [1933] HL

A
  • timber supplied was 25% thicker than specified but yet fit for purpose.
  • HL held the contract term was a strict requirement and the defence could not prove the deviation was minimal.

Key Point: Hard case since remedied by amendments to the SoG 1979 (for commercial contracts only).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Ruxley v Forsyth [1994] HL

A
  • pool manufactured with less depth than stipulated in contract. Safe and no property devaluation proved.
  • HL overturned CA decision for full replacement value and instead granted only a sum for loss of amenity.

Key Point: As a consumer Ruxley should have been entitled to strict interpretation of the contract. Reasonableness cited as the ratio for awarding amenity damages only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cleveland Bridge v Multiplex [2010] CA

A
  • complex litigation over Wembley Stadium.
  • argument over costs awarded under partial performance and if Sumpter v Hedges applies (i.e. doctrine of implied contracts v restitution).
  • ruled that Sumpter v Hedges is still good law where the contract is entire the party in breach has no right to claim for restitutionary costs.

Key Point: Restitutionary claims require a divisible contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Roberts v Havelock (1832)

A
  • shipwright refused to complete repairs until sums due were paid.

Key Point: Repair contracts are generally divisible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Behzadi v Shaftsbury [1992] CA

A
  • Purchaser rescinded purchase contract based on their submission of notice that time was of essence after the other’s party breach of time.
  • Held purchaser in breach since unreasonable length of time stipulated.

Key Point: Notice can be used to make time a condition. Must be reasonable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Union Eagle v Golden Achievement [1997]

A
  • courier arrived 10 min late with contract for flat purchase. Deposit forfeit as liquidated damages since seller refused to accept performance after the deadline.

Key Point: Innocent party has the option to waive a stipulated time performance. No rights accrue to the party in breach when time is a condition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly