Contract law-What are the remedies for a Breach (damages) Flashcards
Constructive condition of exchange
Constructive condition of exchange (CCE)
o Common law—failure to substantially perform means the CCE is not satisfied, so the other side may withhold their own performance
Cannot withhold payment if the other side has substantially performed, but may be entitled to recover for the breach
o UCC—perfect tender: Seller must strictly perform all obligations or be in breach. The doctrine of material breach applies to installment sales.
Anticipatory repudiation
Anticipatory repudiation is closely related to CCE.
What are your remedies when the other side says they will not perform on the contract (repudiation) before performance is due?
- If a party clearly and unequivocally repudiates, the nonbreaching party has two options:
1) Treat the repudiation as a breach and sue immediately for damages - BUT, if you have completed the entire performance and are only waiting for payment, you cannot sue early.
2) Ignore the repudiation, demand performance, and see what happens
- Can a party retract its repudiation?
Yes, as long as the other side has not:
o Commenced a lawsuit; or
o Acted in reliance on the repudiation (by materially
changing its position)
What is the equivalent to anticipatory repudiation in the UCC world?
“reasonable grounds for insecurity about the other side’s performance allows you to demand “adequate assurance of performance”
What are the consequences of demanding adequate assurance of performance?
If the other party does not offer those assurances in a reasonable time then you can treat it as a repudiation.
money damages
they are what you tipically get when someone breaches contract
What are expectation damages?
o This is the normal way to calculate damages in contracts.
o Goal—to put a party in the same economic position it would be in if the contract had been performed as promised.
o
What is the formula for expectation damages?
Measured by comparing the value of the performance without the breach to the value of the performance with the breach.
If you had to pay someone else more money to complete the performance the other breach then your damages are calculated:
Cost to get the full performance- cost of the contract (what you promise to initially pay. the result is what you can recover.
But if getting the performance satisfied costed you less than what you originally contracted then you don’t get any damages
Damages under UCC
Under UCC if the seller breaches. the seller is still entitled to the benefit of his bargain.
What are the limits on expectation damages?
Must be proven with reasonable certainty.
Unforeseeable consequential damages
mitigation
What are unforseeable consequential damages?
Not recoverable unless the breaching party had some reason to know about the possibility of these special damages at the time of contracting (the Hadley rule)
o Two categories of damages:
1) General damages—the type of loss that almost anyone would incur from a breach
* Includes incidental damages—the cost of storing rejected goods, or finding a new buyer, or finding a replacement vendor
2) Consequential damages—losses that are unique or special to this plaintiff
What is required under mitigation?
A breached-against party must take reasonable steps to reduce damages from a breach.
If a party refuses to mitigate, the law will calculate damages as if the party did mitigate.
o The defendant bears the burden of proving a mitigation failure.
o Mitigation efforts must be reasonably similar to the original contract.
Incomplete performance
If the paying party breaches in a partially completed building contract, can the builder continue to work on the job?
This runs counter to mitigation—it would be
“running up the damages.”
o Adjust the recovery to take account of the fact that the builder did not need to finish the job
What are the expectation damages in a situation where there is incomplete performance>
expectation damages= contract price-amount already paid- amount that would be needed to finish the job.