Contract Law - Discharge Flashcards
In what ways can a contract be brought to an end?
- Agreement
- Performance
- Breach
- Frustration
Discharge by agreement
- Parties can agree to end the contract before it has been performed
- Constitutes an agreement to change the original agreement
- Needs to be supported by consideration
Two types of agreement
- Bilateral: both in agreement
- Unilateral: one party discharges the other
Bilateral discharge
- Neither party performs its part
- Both agree to discharge the contract
- Needs agreement, consideration and ITCLR (reflecting freedom to contract)
Bilateral Discharge Case
Berry v Berry 1929: Parties discharged the previous contract to end a new one due to new terms.
Unilateral Discharge
- One party performs the act, in turn discharging the other
Unilateral Discharge Case
MWB Business Exchange Centres Ltd v Rock Advertising Ltd [2016]: Licence agreement had a standard clause ‘all variations to this licence must be agreed, set out in writing and signed on behalf of both parties before taking effect’
Discharge by Performance
- Can be discharged if parties have performed their obligation
- Entire Obligations Rule
Entire Obligations Rule
Contracts must be performed strictly in accordance with their terms. If only one party performs, they are able to bring an action against the other for breach.
Discharge by Performance Case
Cutter v Powell 1795: Widow could not sue for late husbands wages as he died before completing contractual obligations
Entire Obligation Rule: Exceptations
- Substantial performance
- Divisible contracts
- Part performance: ‘quantum meruit’
Substantial Performance
- If a party offered substantial performance under the contract, courts can hold that they discharged their obligations
- Failure to perform terms must be a breach of warranty or non-fundamental breach of an innominate term
- Party can sue and recover appropriate amount
Substantial Performance Case
Hoenig v Issacs 1952: Contract was substantially performed, differed from the contract in minor aspects, court ordered the outstanding amount to be paid to the decorator, minus costs of the defects
Divisible Contracts
- Contracts can be broken into smaller unities
- In an entire contract: person has completed obligations (e.g. Cutter)
- In divisible: person paid in instalments, payments on selected dates, failure to perform entire obligation on one of the parties does not lead to a non-payment.
Part Performance
- One party accepts part performance (voluntarily) then the other is discharged from the contract.
- Innocent party must have a genuine choice as to whether or not to accept part performance
Part Performance Case
Sumpter v Hedges 1898: payment for part performance was refused, D had been left with a half built house and had no choice but to accept. Sumpter not entitled to payment for the work, however was awarded values of materials as they could’ve been returned but Hedges kept them.
quantum meruit
‘What one has earned’
- If performance was started but been prevented by the other party, quantum meruit may be entitled (payment for work done)
- Equitable doctrine based on the premise that no party should be unjustly enriched
- No damages but ‘refund’ due
Discharge by Breach
- A breach can allow the innocent party to discharge the contract
- If the term is a warranty, the innocent part can only claim damages
Anticipatory breach
- D realises they are unable to perform contractual obligations before due date, informing the other party of breach of contract
- Innocent party can accept breach and discharge the contract or refuse to accept breach and insist it is performed anyways.
Discharge by Breach Case
White v Carter Ltd v McGregor 1962: Party may have legitimate interest in the contract being performed rather than accepting the anticipatory breach
Discharge by Breach Remedy
- Repudiation: refusal to perform a duty of obligation owed to the other party
- Terminate the contract - but only if breach is a condition
- Common law remedy (damages)
- Equitable remedies (recission; specific performance; injunction).
Discharge by Frustration
- Contract is discharged by an intervening event outside of the parties control
- When a contract is frustrated there is no longer an obligation to perform, ending the contract
- Doctrine is interpreted narrowly to avoid interfering with freedom of contract
Frustration (three types)
- Illegal to be carried out
- Impossible to be carried out
- Radically different from what the parties agreed
Discharge by Frustration Case
Paradine v Jane 1647: Contract was not discharged by the intervening event (army invasion). Courts stated if Jane wanted to reduce liability they should’ve made an express provision in the lease.