Contract Administration Flashcards
INSOLVENCY
A domestic S/C asks to be paid directly, what do you do?
Highlight to them that payment to domestic subcontractors is the duty of the main contractor.
INSOLVENCY
How would you check to see if a contractor was going into insolvency?
Dun and Bradstreet financial report can be carried out to check their current financial standing. Speak with their sub-contractors and see if they had been paid on time/in accordance with their contracts.
INSOLVENCY
What happens when a contractor becomes insovent and what would you do?
Firstly establish through the bondsman that the contractor was insolvent, then inform the client and design team and advise them to stop all payments to the contractor. Advise to secure the site to prevent and plant or materials from being removed and undertake a detailed valuation of the works completed to ascertain the finantial status of the project. Then advise the client to consider the options available under JCT i.e. either employ another contractor to complete the works,negotiate with the reciver to allow the original contractor to complete the works if they are nearly finished, not complete the works at all or directly employ all sub contractors thus novating the project. Call in all bonds and guarantees to enable the project to be completed. NB if a new contractor is appointed collateral warranties should be checked as it’s unlikely he will cover work done by previous contractor.
INSOLVENCY
What is a notional final account?
The notional final account is the current evaluation of how much the works currently to be undertaken under the contract and any variations instructed is valued at.
INSOLVENCY
If a contractor goes insovent but the client needs the job finishing what options are available to him?
Apoint another contractor, negotiate with original contractors reciever to allow him to complete the works or directly employ the sub contractors himself.
INSOLVENCY
What would happen to the contractors sub contractors?
Their contracts would also be determined.
INSOLVENCY
Could the contractor remove plant after he had become insolvent?
If the contract has been determined properly the contractor would be notified to remove his plant and labour from the site and leave it secure. In reality the receiver would mst likely carry this out.
INSOLVENCY
Can you suspend further payments if a contractor is insolvent?
Clause 8.5.3 under the SBC relieves the employer of their duty to make further payments to the contractor and suspends the contractor’s duty to complete the works.
INSOLVENCY
A sub contractor says the contractor hasn’t paid him in a month, what do you advise?
I am not able to advise them directly. They should seek to resolve the issue with the Main Contractor.
INSOLVENCY
What would you do if the CLIENT goes into recievership?
Advise the client to inform the contractor of his insolvency. It is likely the contractor would then determine his contract and his obligation to complete the works would be suspended. The contractor and S/C would then be allowed to remove their plant and equipment and any materials they still held title to. The contractor would then prpare an application for payment for the works completed so far and the client would be required to pay accordingly within 28 dyas. I would check this submission on the clients behalf and inform him of allof the above. I would also check with the reciever that I would be paid for my services.
RETENTION
What is retention?
Retention is an amount deducted from interim certificates. It acts as an incentive for the contractor to complte the works and return to site to rectify and defects and also provides security for the employer should the contractor default. Projects under £500’000 = 5%, Projects over £500’000 = 3%. Amount of retention contained in appendix to contract.
RETENTION
When is retention released?
Half is released at practicalcompletion and remainder is issued on completion of defects liability period when a certificate of making good defects is issued.
RETENTION
What doesn’t retention apply to?
Retention does not apply to any loss and/or expense monies a contractor maybe entitled to.
RETENTION
Are there any alternatives to retention?
Rentention bonds maybe offered in lieu.
VALUATION / VARIATION
What methods of valuing variations are there?
First check architect has instructed variation. JCT98 C13.5 such as contract rates, contract rates plus fair allowance, fair and reasonable rates. Day works if no other means. As set down in the rules for carrying out valuations unless a contractors price statement or quotation under 13A have been accepted.
VALUATION / VARIATION
What is included in a valuation?
Total value of meausred works including variations instructed, variations treated under the contract as if they were instructed, all works instructed relating to Prov Sums and all works for which an approx quantity has been inserted in the Bill. Listed items for Materials off site. Amounts for each Nominated S/C. Profits due on the Nominated S/C works.
Items in valuation not subject to retention:
Statutory fees, Opening up for inspection works, Any amounts due L&E and Antiquities, Any amounts relating to early final payment of Nominated S/C, Any amount payable under Clause 38 (contribution, levy and tax fluctuations) and Clause 39 (labour and materials cost and tax fluctuations).
VALUATION / VARIATION
How would you value materials on site?
Contractor issues list of materials he is claiming for, clients QS then visits site to value materials. JCT C.30 states materials on site should only include items which are reasonabley, properly and not prematurely delivered to site.
VALUATION / VARIATION
How would you value materials off site?
Check if item is listed in contract, then check claim isn’t too far In advance of the programme. Request a vesting certificate to confirm transfer of title to contractor, visit storage facility to check items are stored seperatley and clearly marked for project, ensure items are insured against loss and damage, check a bond had been taken up for uniquely identified items, check invoice as proof of payment from contractor. Recommend payment in interim certificate and pass to arcitect so they can isue certificate.
VALUATION / VARIATION
If no materials were listed in the contract for payment off site would you still pay for materials off site?
No
VALUATION / VARIATION
What is a vesting certificate?
A vesting certificate confirms the transfer of title to the contractor.
VALUATION / VARIATION
Would you include defective materials in a valuation?
Any defective materials on site would be deemed ineligible for payment, however some wastage factors are applied to masonry materials so a limited amount is permissible. Defective materials off site would not be payable.
VALUATION / VARIATION
How would you value defective materials?
Using the contract rates where possible. Or a on the basis of measurement and first principles i.e. material cost only.
VALUATION / VARIATION
would you include contra charges would you include in a valuation?
Contra charges in my experience are only included in CM contracts. Otherwise under traditional, D&B and MC they are the responsibility of the Main Contractor to deduct from their own valuations.
VALUATION / VARIATION
Who is responsible for assessing valuations under JCT 98?
CA who can then instruct the QS to ascertain the value the works on their behalf.
VALUATION / VARIATION
Would you include architects verbal instructions?
Only if supported by an AI within 2 days of the CVI being issued.