Can you expand on your knowledge of the JCT Standard Building Contract
The JCT SBC allows for additional to the intermediate contract such as:
Employers representative, listed sub contractors, retention bonds, variation and acceleration quotations, third party rights
What JCT Contracts allow for a Clerk of Works?
- JCT Standard building contract
- JCT Intermediate Contract
- Not JCT MW
What contract allow for sectional completion and named sub contractors?
Intermediate and standard building contract
Can you talk me through the Extension of time timeline?
Can you explain the interim payment procedure under JCT MW ?
What is sectional completion?
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
What type of contracts
Traditional
Design and build
Construction management contracts
What’s the procedure claiming an EOT
The contractor need to write to the client