Can you expand on your knowledge of the JCT Standard Building Contract

A

The JCT SBC allows for additional to the intermediate contract such as:

Employers representative, listed sub contractors, retention bonds, variation and acceleration quotations, third party rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What JCT Contracts allow for a Clerk of Works?

A
  • JCT Standard building contract
  • JCT Intermediate Contract
  • Not JCT MW
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What contract allow for sectional completion and named sub contractors?

A

Intermediate and standard building contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you talk me through the Extension of time timeline?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you explain the interim payment procedure under JCT MW ?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is sectional completion?

A

Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What type of contracts

A

Traditional
Design and build
Construction management contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the procedure claiming an EOT

A

The contractor need to write to the client