Contract Administration Flashcards
Do RICS provide any guidance on Contract Administration?
Yes - RICS Contract Administration Guidance Note 1st Edition.
(This only covers JCT minor works, intermediate and standard building contracts)
What is the role of a Contract Administrator?
Administering the contract in a way that correct contractual and administrative procedures are followed, and the life of a building contract from inception to completion is accurately recorded.
What does the CA need to include for in a final Adjusted Contract Sum (ACS)?
Cost for: Prelims Specified Works Outstanding/Unspent PC and contingency sums Additions/Omissions Employer Variations Anticipated Variations Loss and Expense Prolongation Costs Potential Contractor Claims
What do building contracts state about interim valuations?
The basis on which interim valuations are to be carried out;
What sums should be included in the valuations;
Against what elements retention monies should be allocated.
Give some examples of certificates/notices that a CA may issue as part of a building contract.
Contract Completion Date Notice
Extensions of Time Certificate
Early/Partial Possession Certificate
Sectional Completion Certificate
Practical Completion Certificate
When may conflict arise between the CA and Employer?
Where the CA gives advice to the employer or instructs the contractor on variations (e.g. specifying substitute materials, changes in layout, giving verbal instructions on site).
Giving advice to the employer during the early stages of a project where the employer is deciding what is wanted for a project.
Specifying materials, the performance of which will affect the works.
Appointment of a Contract Administrator:
The surveyor when acting as CA should comply with RICS rules and by-laws relative to terms of appointment including:
- Confirming the terms and conditions of the appointment in writing.
- Detailing the services to be provided.
- Confirming the basis of fees to be charges for those services.
- Identifying that a Complaints Handling Procedure exists.
Appointment of a Contract Administrator:
What exact details need to be agreed with the Employer at the outset?
A clear explanation of the scope of services to be provided;
A clear indication of what services will not be included within the appointment;
Information on how the appointment may be terminated by either party;
A dispute resolution procedure (mandatory where the employer is a business);
The level of PII to be provided, the level of which depends on the nature and extent of the project.
Where may the CA need to issue an instruction to change works?
Additional / Unforeseen Works;
The employer changes their mind.
What are the 2 types of provisional sums?
‘Defined’ - where the provisional sum given is for defined work, and the contractor will be deemed to have made due allowance in programming/pricing preliminaries.
‘Undefined’ - the contractor will be deemed to have NOT made any allowance in programming/pricing preliminaries.
What is a Loss and Expense Provision?
Loss and Expense Provisions provide for the contractor to be reimbursed for deferment of possession or the regular process of the works having been affected by certain specified circumstances, where the contractor will not be reimbursed by other provisions of the building contract.
What is a Letter of Intent?
Letters of Intent are typically used to facilitate a start of works on site, pending agreement of the contract terms, and so strictly speaking the role of CA is unlikely to commence at this stage.
Tell me about the Housing Grants, Construction and Regeneration Act 1996?
Also known as ‘The Construction Act’.
Introduces new procedures into construction contracts to primarily deal with dispute resolution and ensuring cash flow is maintained.
Procurement:
What are the 3 main procurement options?
(as detailed in ‘Deciding on the Appropriate JCT Contract 2016’)
Traditional Procurement
Design and Build Procurement
Management Procurement
What is Traditional Procurement?
Where the design process is separate from construction, and full documentation is required before the contractor can be invited to tender for carrying out the works.
Appointment of contractor is by competitive tender.
Client has responsibility over design, quality, standards etc. through his appointed consultants. i.e. no design responsibility on the contractor.
Overall project programme can be longer as design and construction are separate processes.
Client has reasonable certainty on costs; as a contract figure is known at the outset.