Contract Admin Flashcards

1
Q

What is a letter of intent?

A

A letter of intent is a document expressing an intention to enter into a contract at a future date but creates no contractual relationship until that future contract has been entered into.

They can be used as an interim arrangement to mobilise construction prior to a formal contract being executed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are FDIC based contracts?

A

International Federation of Consulting Engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is the NEC suite?

A

New Engineering Contract

On NEC4 - allows for collaboration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Joint Contracts Tribunal (JCT) Suite of documents

A

The suite of contracts drafted by the Joint Contracts Tribunal (JCT) in England is adapted for Scottish law by the Scottish Building Contract Committee (SBCC)

‘JCT contract’, it is typically in reference to a standard building contract.
JCT contracts are usually made between an ’employer’ and a ‘contractor’ to facilitate the process of delivering a building project.

They set out:
- Relevant terms and conditions, including the obligations of the parties

  • The costs involved and specification of the project. This allows all parties to see exactly what needs to be done, when it needs to be done, who needs to do the work and what the cost will be.
  • Crucially, a JCT contract provides clarity on the roles and responsibilities of each party to try to ensure a smooth delivery of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the different types of SBCC contract?

A

Minor works
design and build
standard
Measured Term
home owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use a minor works contract?

A
  • where the work involved is simple in character;
  • where the work is designed by or on behalf of the Employer;
  • where the Employer is to provide drawings and/or a specification and/or work schedules to define adequately the quantity and quality of the work; and
  • where an Architect/Contract Administrator or Quantity Surveyor, if appointed, is to administer the conditions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When would you use a standard contract?

A

The Standard Building Contract continues to be published in three versions: With Quantities (Q), Without Quantities (XQ) and With Approximate Quantities (AQ).

Each continues to include the provisions designed to meet the needs of both private and public sectors.

The Contract is primarily appropriate for larger works where most of the works have already been designed and/or detailed by or on behalf of the Employer, where detailed contract provisions are required and where the Employer is to provide the Contractor both with drawings and with either bills of quantities (Q and AQ) or a specification or work schedules (XQ) to define the required quantity and quality of the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When would you use design and build?

A

DB/Scot 2016 is primarily appropriate for larger works where the Employer has defined his requirements and where the Contractor is not only to carry out the works, but also to complete the design for them in accordance with those requirements.

It retains the provisions designed to meet the needs of both private and public sectors and allows for the works to be carried out in sections. For the purpose of contract administration, DB/Scot 2016 requires the appointment of an Employer’s Agent; that agent may be either an external consultant or an appropriate member of the Employer’s staff.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When would you use Measured Term?

A
  • by Employers who have a regular flow of maintenance and minor works, including improvements, to be carried out by a single contractor over a specified period of time and under a single contract;
  • where the work is to be instructed from time to time and measured and valued on the basis of an agreed schedule of rates; and
  • where a Contract Administrator is to administer the conditions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Housing Grants, Construction and Regeneration Act 1996?

A

is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.
Provisions of the act include:
 The right to be paid in interim, periodic or stage payments.
 The right to be informed of the amount due, or any amounts to be withheld.
 The right to suspend performance for non-payment.
 The right to adjudication.
 Disallowing pay when paid clauses.
The Act applies to all contracts for ‘construction operations’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you tell me the current changes to the SBCC JCT suite 2024

A

The SBCC will be release Scottish complaint documents over this year.

Changes aim to:

Modernise and Streamline
- gender neutral language
- flexibility of electronic notices

New contract
- JCT Target Cost Contract

Legislative Changes
- Changes to building regs, insolvency and payment provisions

Future Proofing
- provisions for collaborative working
- Sustainable development and environmental considerations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the key sections of a JCT minor works contract?

A

Agreement
- Contract agreement between the parties

Recitals
- background to the contract

Articles
- Contractors obligations
- Contract sum
- Role of the the architect/CA
- PD
-CA

Contract particulars

**Conditions

  • Definitions
  • Carrying out the works
  • Control of works
  • Payment
  • Injury, Damage and insurance
  • Termination
  • Settlement of Disputes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an Interim valuation certificate?

A

Is a document that specified the amount due to a contractor for work that has been completed.

It is designed to maintain cash flow during a construction project

Allows under the Housing grants, construction and regeneration act 1996

would include:
1) Prelims
2) Measured Works
3) Materials on / off site
4) Variations
5) claims
6) retention
7) previous payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the key dates in relation to interim payment under SBCC 2016

A

For Minor Works:

** Interim Valuation Date

  • Specified in the contract particulars
  • Usually one month after date of possession
  • Contractor submits a payment application
  • This can include all works completed to the interim valuation date, materials that have been ordered and any variations or changes to the work.

** Due Date

The due date is 7 days after the interim valuation date and triggers the payment cycle

** Interim Certificate

CA or arch must issue a interim certificate no later than 5 days after the due date. This document values the amount due to the contractor for work done and possibly materials bought on site

If no interim certificate or pay less notice is issued, the contractor may issue a payment notice in which case the client must pay the payment notice in full.

** Final Date for Payment

14 days from the due date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What happens if you do not agree with the contractors valuation?

A

If the CA disagrees with the contractors valuation in the payment application, they can issue a Pay Less Notice.

This must include the amount the CA considers due and the basis for how this was calculated.

Must be issued 5 days before the final date for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happens if the CA doesn’t issue a payment application

A

Under minor works
- The CA must still issue a Interim certificate regardless.
- If they don’t, the contractor may issue a payment notice.

Under Design and Built
- A interim payment application is required.
- If it is not received by the valuation date, the due date will become 7 days after it is received.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the key components that should be included in a interim payment certificate

A

Details of the contract Sum

Value of the works completed to date

Previous payments

Current payment due

Any retention or deductions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What can be included in a contractors loss and expense?

A

Refers to additional costs incurred due to delays or disruptions caused by an employer related reason. can include:

Delay related costs (Prolongation)

Increased labour or material costs

Extended site overheads

** Not always entitled
- if other contractor delays are also present, there may no be no loss.
- must be regular progress of works being materially affected by relevant matter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the usual retention ?

A

Depends on contract particulars.

Usually a default of 5% until practical completion and 2.5% being until defect liability period has expired.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How can a sub-contractor be appointed under JCT?

A

3 ways

Domestic Sub-contractors
- Selected, Procured and awarded packages at the discretion of the contractor

Nominated Subcontractors
- These are pre-selected by the client and then imposed on the contractor.
- Provisions not included in some JCT as it is complicated of who is reponsible for their performance

Named Subcontractors:
- The names at lease 3 companies and the contractor chooses one.
- This avoids the client retaining responsibility for the sub-contractor and can hold the contractor responsible for any issues that arise from their work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the base date in JCT?

A

Usually the date of the tender or priced offer

contract sum deemed to have been calculated at the base date

Any increase cost due to inflation after the base date would be borne by the contractor, not the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How are Fluctuations dealt with under JCT?

A

They are dealt with through specific provisions that allow adjustments to the contract price

Option A
Deals with fluctuations to contributions, taxes and levies (statutory)

Option B
Additionally covers labour and material costs

Option C
Formula adjustment using the formula rules.
different work categories and exclusions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the date of commencement ?

A

Is the date when the contractor is required to start the work on site

Client must issue a Notice to Commence

Interim Valuation Date which triggers payment cycle in related to commencement date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What happens if the client does not issue a notice to commence?

A

Must notify the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

what is a relevant event under JCT?

A

A relevant event under SBCC refers to a specific event or circumstances that may impact:
- progress
- completion
- cost of a construction project

They provide grounds for an extension of time or additional payment

26
Q

Can you name some examples of relevant matters?

A

Exceptionally adverse weather

Failure to provide information

The supply of materials and goods by the client

Delay in giving the contractor possession of the site

Force major

27
Q

What is a relevant matter?

A

For a contractor to claim loss and expense a relevant matter must have occurred.

A relevant matter is when the client is responsible for an event that materially affects the progress or cost of works.

This enables the contractor to claim direct loss and/or expenses

28
Q

What is exceptionally adverse weather conditions?

A

No definition within JCT

in practice, weather that was unforeseen for a time of year and significantly disrupt construction works

29
Q

What is Force Majeure?

A

Extraordinary and unforeseen occurrences which frees the parties in an agreement from certain obligations to one another.

Wars
Natural disasters
Terrorist attacks
Epidemics

30
Q

How did Covid 19 affect JCT contracts?

A

If a project is suspended (Usually 2 months) either party may terminate the contract by giving notice.

Covid 19 was a Force Majeure event

Increased costs, so may allow for loss and expense if provisioned in contract/

31
Q

What is a concurrent delay under JCT

A

Refers to two or more delay events occurring at the same time

One is the employers fault

Once is the contractors

In the case the contractor is generally entitled to an extension of time for the relevant event (employers responsibility)

32
Q

What is acceleration under JCT?

A

When employer or parties agree to try and bring the completion date forwards.

Usually done be re-sequencing or deployment of additional workers.

Employer may have a contractual right to require acceleration completion.

JCT provided acceleration quotation. Identifies time saved and adjustment to contract sum.

must include direct costs, may allow for consequential loss and expense depending on contract and an allowance for preparing the quotation

33
Q

What is deceleration under JCT

A

If the construction contractor is directed in writing or constructively to slow its job progress.

If project delays result from deceleration, the contractors overhead costs may be recoverable.

34
Q

How are instructions dealt with under JCT?

A

CA or architect can instruct changes to the works through a Contract Instruction.

If the contractor doesn’t implement the instruction, the employer can issue notice to the contractor

If after 7 days the contractor fails to implement the instruction, the client may employ others to do the work and the additional costs can be deducted from the contractor

35
Q

How are variations dealt with?

A

Value to be agreed by the contractor and employer. If they can’t then by the CA/Architect on a fair and reasonable basis using rates from bill of quantities

if a significant variation, it may be dealt as a relevant event can be granted additional time

Same as instruction protocol, if contactor doesn’t do it after notice and 7 days can get someone else to complete works and deduct from contractor

36
Q

How are adjustments to the completion date (extension of time) dealt with?

A

Relevant event can cause an adjustment of the completion date

If there is a delay due to completion due to a relevant event, then the CA must give notice in writing setting out a ‘fair and reasonable’ extension of time as specified in the contract.

Notice of Delay

Contractor must serve notice of a delay in writing to the employer when it becomes reasonably apparent that works will be or are likely to be delayed.

Claim and Extension of Time

Can be claimed by delays caused by the employer or delays under the contract that are not the contractors responsibility.

37
Q

What is a non-completion certificate?

A

gives formal written notice to the contractor that they have failed to complete the works described in the contract by the completion date that was last agreed

Some contracts require the CA to issue a non-completion certificate as prerequisite to claiming liquidated and ascertained damaged.

CA must give consideration for an extension of time before issue.

** Not required under minor works, but still considered best practice to issue one any way

38
Q

What happens for non-completion for sectional completion?

A

Separate non-completion certificates must be issued for each section that is not completed by the required date.

39
Q

What happens to a non-completion certificate if an extension of time is later granted?

A

The extension of time shall cancel that certificate

40
Q

What are liquidated damages?

A

Pre-agreed amount of money that a party (usually the employer) can claim from another party (usually the sub-contractor)

used as compensation for a specific breach of contract, typically a delay in the completion of works. It is only an estimate of a hypothetical breach, but must be realistic.

41
Q

What notices are required for liquidated damages

A

Under a standard JCT

**Must issue a non-completion notice

**(First notice) Before the due date, the employer may require payment, withhold or deduct liquidated damages.

**(Second Notice - Deduction notice)
No later than 5 days before the final date for payment of the amount payable under the contract, to give a notice requiring the contactor to pay liquidated damages.

If liquidated are to be deducted from other sums due, then a pay less notice must be issued.

42
Q

What is suspension under JCT?

A

Suspension under JCT Refers to the temporary halt of construction work due to certain circumstances.

** Right of payment
If the employer fails to pay a sum by the final date of payment and the failure continues for 7 days after giving notice to suspend performance. The contractor may suspend until payment is made in full.

Will be entitled to costs and expensed reasonably incurred by exercising their right.

** Force Majeure
Both the employer and contractor can terminate a JCT if there is a prolonged suspension (usually 2 months)

** Insolvency
Under JCT, the contractors obligations to carry out the works is automatically suspended in the event of insolvency.

43
Q

Termination

A

(First Notice)
- This is a notice to inform the contractor that they are in default
- May be due to not working regularly and diligently
- or Suspended works

(Second Notice)
If default continues for 7 days:
- The employer may on, or within 10 days from this period, give notice to the contractor terminating their employment.

44
Q

What is sectional completion under JCT?

A

Refers to provisions under the contract that allow different completion dates to be set for different sections of the works

45
Q

What must be in place for sectional completion?

A

**Defining Sections
- Sections must be clearly defined in contract particulars.
- this allows for different completion dates.

**Completion certificate
-CA must issue a Sectional Completion Certificate or a ‘Non-Completion Certificate’ for those sections

If Sectional completion is granted, this will transfer liabilities for works, maintenance and insurance form the contractor to the employer. This will trigger the commencement of rectification and warranty periods.

**Liquidated damages
If a contract provides for sectional completion, then separate liquidated damages can also be agreed for each section of the works.

46
Q

What is partial possession?

A

It is a provision under the contract that allows the employer to take possession of part of the works before practical completion

The contractor must consent to the employer taking possession.

If the employer takes possession it counts as practical completion

47
Q

What are the implications of the employer taking partial possesion?

A

The defect liability period for that part commences

Responsibility and insurance for that part transfers from the contractor to the employer

The employers right to liquidation damages ceases for that part.

A percentage of retention is usually released for that part.

48
Q

What is practical completion? (Penultimate Cert)

A

No definition under JCT

Usually defined as when as a building is complete bar from any minor defects.

It is a key milestone in a construction project.

49
Q

What are the implications of practical completion?

A

Releases half of retention money

Ends contractor liability for Liquidates damages

Start of the Defects Liability Period

50
Q

What is the Rectification period?

A

Begins on certification of the practical completion

It is a period that typically lasts 6 to 12 months

During this period the client reports any defect that arise to the contract administrator.

The CA decide if they are defects or maintenance issues

CA may then issue instructions for the contractor to make good within a reasonable time.

It is the contractors responsibility to identify and rectify defects.

51
Q

What happens at the end of the rectification period?

A

The CA produces a schedule of Defects listing defects that have not been rectified.

Will agree with the contractor the date they will be rectified.

When all defects on the schedule have been rectified, the they issue a certificate of Making Good Defects.

Client then does have a right to insist that the contractor rectifies defects not notified during that period.

52
Q

What happens if defects are found after the rectification period?

A

Client must seek address:
Damages
Breach of contract
or negligence

Statutory period 6 years for simple contract

12 years for a contract under seal

53
Q

What is a final certificate?

A

Issued by the contract administrator that a construction contract has been fully completed.

Issued at the end of the defects liability period.

This releases any retention and money owed to the contractor.

54
Q

What is a Latent and Patent defect?

A

Paten
- Defects are visible and easily recognisable.
- May be defective as work not carried out in accordance with the contract

Latent
- These are hidden defects that are not easily discovered during an inspection.
- May come apparent years later

55
Q

What is an inherent defect

A

Defects that are not immediately apparent

often associated with a flaw that is intrinsic to the material or construction process

56
Q

What insurance is available under JCT

A

Option A
Contractor is required to take out and maintain a joint names policy insurance for all works

Option B
Employer is required to take out and maintain a joint names policy insurance for all works

Option C
The Employer is required to take out and maintain (a) a Joint Names Policy in respect of the existing structures and their contents, and (b) a Joint Names Policy for all risks insurance for the works.

Option C is for works to existing buildings

57
Q

what insurance is required under JCT

A

**Standard Insurance options A-C

**Public liability insurance
-covers death or injury to third parties
- damage to other peoples property

**Professional liability insurance
- Insurance against liabilities arising from professional negligence
- Architects, Engineers, CA, that owe a responsibility to the employer.

option for 6.51 insurance protect against costs from non-negligent damage to property.

58
Q

what are bonds, guarantees and warranties?

A

Bonds
- typically issues from a bank
- guarantees completion of a project by a contractor
- Can a be performance bond or guarantee

Guarantees
- Right for compensation in the event the contractor fails to carry out their obligations

Warranties
- Agreements that certain stipulations in the contract are true
- provide reassurance that the one party will perform
- often given to suppliers to protect against defects or failures in work

59
Q

What are the key differences between JCT Minor Works, Intermediate
and D&B Contracts?

A

Minor works has 7 sections of conditions instead of 9.

No provisions for named sub-contractors

No mention of bonds or collateral warranties

No provisions for sectional completion

No relevant events listed

D&B has no CA and has employers agent

No option B - name all risk insurance

60
Q
A