Contract 4 Remedies Flashcards
Rule on determining if a term is a condition or warranty
Generally, if the effect of a breach of the term deprives the innocent party of the whole benefit of the contract, the term is a condition; if not it is a warranty.
Exceptions to the doctrine of complete performance and their respective remedies
(3) SUV
Substantial performance:
work is finished but defective.
Slight or extensive defect is by considering the cost of cure.
Hoenig v isaacs: 1/14 of contract price - minor defect
Bolton v Mahadeva 1/3 of contract price - extensive
Unjust/Wrongful prevention of performance by the other party
Remedies: recovery of damages and lost profits. quantum meruit; quantum valebant
Voluntary acceptance of partial performance by the other party (Sumpter v Hedges)
D must be free to choose to accept or not.
Remedy: quantum meruit
Define divisible obligations
parties have agreed payments for a distinct part or stage of the work.
Broad ethos of damages for breach of contract
2
Compensatory: the goal is to compensate the claimant, not punish the D.
C must have sustained loss or C may have to pay D’s cost (Obagi v Stanborough (Developments) Ltd)
Obagi v Stanborough (Developments) Ltd
D broke a term promising best endeavour to secure planning permission. There was never any chance. C sued. Court awarded nominal damage and ordered C to pay for D’s costs.
Loss is needed for damages to be granted or else C may have to pay D’s costs
Factors consider with calculating damages on expectation loss basis
ADORE
(5)
Loss of amenity (Ruxley) A
Loss of opportunity (Chaplin v Hicks) O
Cost of cure/repairs (services) R
Difference in value (current price paid to find replacement) D
Loss of pleasure (enjoyment) (only if pleasure is an important aim of the contract) E
Ruxley Electronics and Contruction v Forsyth
Pool built not with the depth requested. Difference in value between a correct pool and the existing oneis nil. Forsyth sued for cost of cure which is excessively high.
Held in this case, loss is related to the consumer surplus, C will be able to recover for loss of amenity.
Jarvis v Swan’s Tours and Farley v Skinner
C bought a holiday package which turned to be a catalogue of disaster. lawsuit was accepted since the main aim was for enjoyment and damages can be awarded
Surveyor hired to assess if property to be purchased will be affected by noise. Report came back in the negative but turned out to be untrue. Held damages was awarded for non pecuniary loss.
Enjoyment and peace of mind happens to be the main aim of the contract, damages can be awarded.
Statutory authority for contributory negligence
Law Reform (Contributory Negligence) Act 1945
Define penalty clause
EU
A penalty clause is one that attempts to put exorbitant or unconsicionaable economic pressure on a party to perform the contract.
A penalty is unenforceable. Where the clause is a penalty, the court is free to assess damages in the usual way and the usual principles of measure of damages, remoteness and mitigation will apply
Chaplin v Hicks
C was shortlisted for a talent show but organiser failed to tell her the timeand place of audition. Held she was entitled to damages to compensate for the loss of change of being one of the final 12 winners.
Damages can be awarded for lost opportunity
Cavendish Square Holding BV v Makdessi - Penalty clause test
secondary primary obligation
a clause is a penalty clause if it creates a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation
Extra criteria for making out a penalty clause as laid down by Dunlop Pneumatic Tyre Co Ltd
(3)
if the sum is extravagant/unconscionable - penalty
withholding payment/more than contract price - penalty
If a single sum is due on the happening of one of mutiple events, varying in severity - penalty
Broad ethos of resitution
Prevention of unjust enrichment of one party
Golden Strait Corporation v The Golden Victory
Ship chartered to D, allowing exception for cancellation if there is war. D repudiated contract nonetheless. Qs on how dmgs should be assessed given that war broke out immediately after.
Dmgs should be assessed by time of breach. The principle is to cover the loss suffered, so the rule will not apply if the key principle is offended