CONSTRUCTION TERMS PART 2 (finalize) Flashcards

1
Q

supports the weight of the structure and its applied loads

A

foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

the simplest and probably the most common type of building foundation that include individual footings, combined footings, and mat foundations

A

spread footing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

consist of a heavily reinforced concrete slab extending under the entire structure, in order to spread the structure’s load over a large area

A

mat or raft foundations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a type of mat foundation in which the weight of the soil excavated approximately equals the weight of the structure being erected

A

floating foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

the process of improving soils in place

A

ground modification or soil stabilization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

nothing more than a column driven into the soil to support a structure by transferring building loads to a deeper and stronger layer of soil or rock

A

pile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

may be manufactured in almost any desired size or shape

A

precast concrete piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

also called shell piles

A

cast–in–place concrete piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

constructed by driving a steel shell into the ground and then filling it with concrete

A

cast–in–place concrete piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

capable of supporting heavy loads, can be driven to great depth without damage, and are easily cut and spliced

A

steel piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

piles made up of two or more different materials

A

composite piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

they are a special form of cast–in–place concrete pile in which an enlarged base (or bulb) is formed during driving

A

bulb piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

simply a column, usually of reinforced concrete, constructed below the ground surface

A

pier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

a structure used to provide all–around lateral support to an excavation and may be either open or pneumatic

A

caisson

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

also known as quicksand

A

liquefaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

a condition wherein the soil behave like a liquid when the water pressure exactly equals soil weight

A

liquefaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

a condition wherein the water pressure is strong enough to move subsurface soil up through the bottom of the cut

A

boiling or piping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

provides lateral support for the sides of an excavation

A

shoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

nothing more than sheeting placed horizontally

A

lagging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

sheeting of concrete, steel, or timber that is designed to be driven by a pile driver

A

sheet piling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

used in place of shoring to protect workers during trenching operations

A

trench shields or trench boxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

the process of removing water from an excavation

A

dewatering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

the ease with which water flows through the soil and primarily a function of a soil’s grain size distribution

A

soil permeability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

the perforated assembly placed on the bottom of the inlet pipe for a well

A

wellpoint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

wellpoints that are sealed at the surface by placing a ring of bentonite or clay around the well casing

A

vacuum wells

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

the process of accelerating the flow of water through a soil by the application of a direct current

A

electroosmosis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

the process of injecting a grouting agent into soil or rock to increase its strength or stability, protect foundations, or reduce groundwater flow

A

grouting or pressure grouting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

slabs that are supported directly by columns without the use of beams or joists

A

flat slabs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

concrete that has been cast into the desired shape prior to placement in a structure

A

precast concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

concrete to which an initial compression load has been applied

A

prestressed concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

places the prestressing material (reinforcing steel or prestressing cables) under tension in the concrete form before the member is poured

A

pre–tensioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

places the prestressing steel (usually placed inside a metal or plastic tube cast into the member) under tension after the concrete member has been erected

A

post–tensioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

the process of removing air voids in concrete as it is placed

A

consolidation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

the process of bringing the surface of concrete to its final position and imparting the desired surface texture

A

finishing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

may be employed to reduce the amount of free water present in plastic concrete after the concrete has been placed and screeded

A

vacuum dewatering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

five (5) most common masonry pattern bonds

A
  • running bond
  • common bond
  • Flemish bond
  • English bond
  • stack bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

uses only stretcher courses with head joints centered over stretchers in the course below

A

running bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

uses a header course repeated at regular intervals; usually every fifth, sixth, or seventh course

A

common bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

alternates stretchers and headers in each course with headers centered over stretchers in the course below

A

Flemish bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

made up of alternate courses of headers and stretchers, with headers centered on stretchers

A

English bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

provides no interlocking between adjacent masonry units and is used for its architectural effect

A

stack bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

a continuously reinforced horizontal beam of concrete or masonry designed to provide additional strength and to prevent cracking in a masonry wall

A

bond beam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

in masonry walls, these are used to permit differential movement of wall sections caused by shrinkage of concrete foundations and floor slabs, temperature and moisture changes, and foundation settlement

A

expansion or control joints

44
Q

consists of layers of impervious material used to seal out moisture or to direct any moisture that does penetrate back to the outside

45
Q

a graphical schedule relating progress of items of work to a time schedule

A

bar graph or bar chart schedule

46
Q

utilizes probability concepts to deal with the uncertainty associated with activity time estimates

A

Program Evaluation Review Technique (PERT)

47
Q

assigns each activity a single fixed duration

A

Critical Path Method (CPM)

48
Q

in this format, each activity is represented by an arrow that has an associated description and expected duration

A

activity–on–arrow

49
Q

they do not represent any work and, hence, always have a duration of zero

A

dummy activity

50
Q

the earliest time at which each event may occur based on an arbitrary starting time of zero

A

early event time

51
Q

that path through the network which establishes the minimum project duration

A

critical path

52
Q

the amount of scheduling leeway available to an activity

A

float (slack in PERT terminology)

53
Q

a simple form of the activity on–node diagram

A

circle diagram or circle notation

54
Q

each activity is represented by a circle containing the activity description, an identifying number, and the activity duration

A

circle diagram or circle notation

55
Q

an extension of the activity on–node format that provides for incorporation of lag-time factors as well as permitting additional precedence relationships

A

precedence diagram

56
Q

all activities are scheduled to start at the earliest allowable time, such a schedule

A

early start schedule

57
Q

all activities are started at their latest allowable starting time

A

late start schedule

58
Q

fixed costs that are incurred each year whether the equipment is operated or not

A

owning costs

59
Q

five (5) principal elements of owning cost

A
  • depreciation
  • investment cost or interest
  • insurance cost
  • tax cost
  • storage cost
60
Q

incurred only when the equipment is used

A

operating costs

61
Q

represents the decline in market value of an item of equipment due to age, wear, deterioration, and obsolescence

A

depreciation

62
Q

represents the annual cost (converted to an hourly cost) of the capital invested in a machine

A

investment cost or interest

63
Q

represents the cost of fire, theft, accident, and liability insurance for the equipment

A

insurance cost

64
Q

represents the cost of property tax and licenses for the equipment

65
Q

represents the cost of rent and maintenance for equipment storage yards and facilities, the wages of guards and employees involved in handling equipment in and out of storage, and associated direct overhead

A

storage cost

66
Q

sum of depreciation, investment, insurance, tax, and storage

A

total equipment owning cost

67
Q

represents the cost of oil, hydraulic fluids, grease, and filters as well as the labor required to perform routine maintenance service

A

service cost

68
Q

represents the cost of all equipment repair and maintenance

A

repair cost

69
Q

it includes cost estimating prior to bidding or negotiating a contract, forecasting project income and expenditure (or cash flow), and determining the amount of work that a construction firm can safely undertake at one time for a construction project

A

financial planning

70
Q

it involves estimating the total cost to carry out a construction project in accordance with the plans and specifications

A

cost estimating

71
Q

involves the measurement and recording of project costs and progress and a comparison between actual and planned performance

A

project cost control

72
Q

determination that the contractor possesses both the technical and financial ability to perform the work required by the contract

A

qualification of a contractor

73
Q

under this procedure only those contractors determined to be capable of performing are invited to submit bids for the project

A

prequalification

74
Q

guarantees that a contractor will provide the required performance and payment bonds if awarded the contract

75
Q

guarantees completion of the project as described in the contract documents

A

performance bond

76
Q

guarantees the payment of subcontractors, laborers, and suppliers by the contractor

A

payment bond

77
Q

contracts between a prime contractor and secondary contractors or suppliers

A

subcontracts

78
Q

one negotiated between an owner and a construction firm

A

negotiated contract

79
Q

provides a specified payment for completion of the work described in the contract documents

A

lump–sum contract

80
Q

specify the amount to be paid for each unit of work but not the total contract amount

A

unit–price contracts

81
Q

contains a provision whereby the contract value is adjusted according to a specified price index

A

fixed price with escalation contracts

82
Q

part of a cost contract in which the contractor is paid a fee that is a percentage of the project’s actual cost

A

cost–plus percentage

83
Q

four (4) construction contract documents

A
  • agreement
  • conditions of the contract (usually general conditions and special conditions
  • plans
  • specifications
84
Q

describes the work to be performed, the required completion time, contract sum, provisions for progress payments and final payment, and lists the other documents making up the complete contract

85
Q

contain those contract provisions applicable to most construction contracts written by the owner

A

general conditions

86
Q

contain any additional contract provisions applicable to the specific project

A

special conditions

87
Q

the analysis of a design with the objective of accomplishing the required function at a lower cost

A

value engineering

88
Q

the time allowed (expressed as either days allowed or as a required completion date) for completion of a construction project is normally specified in the contract along with the phrase “time is of the essence”

A

contract time

89
Q

part of a contract which may be used to simplify the process of establishing the amount of damages resulting from late completion

A

liquidated damages clause

90
Q

drawings that show the location, dimensions, and details of the work to be performed

A

construction plans

91
Q

provide the detailed requirements for the materials, equipment, and workmanship to be incorporated into the project

A

construction technical specifications

92
Q

drawings, charts, and other data prepared by a contractor or supplier which describe the detailed characteristics of equipment or show how specific structural elements or items of equipment are to be fabricated and installed

A

shop drawings

93
Q

these are made at the interval specified in the contract, usually monthly or upon completion of certain milestones

A

progress payments

94
Q

it is customary to withhold a percentage of the value of work completed as a guarantee against defective work and to ensure that the remaining work can be completed within the unpaid amount of the contract; the amount withheld is referred to as _____

A

retainage or retention

95
Q

the usual construction contract contains a clause authorizing the owner or owner’s representative to order changes to the project within the general scope of the contract; the document directing such a change is referred to as a _____

A

change order

96
Q

frequently, it will be found that changes or delay in one activity will necessitate changes in resource allocation or progress on other activities that result in additional project cost; these costs are sometimes referred to as _____

A

consequential costs

97
Q

_____ in the orderly progress of a construction project may result from a multitude of causes

98
Q

three (3) general categories of delay include

A
  • those beyond the control of either the contractor or the owner (“acts of God”)
  • those under the control of the owner
  • those under the control of the contractor
99
Q

the list of deficiencies to be corrected which is prepared at the final inspection

A

punch list of record

100
Q

a request by the contractor for a time extension or for additional payment based on the occurrence of an event beyond the contractor’s control that has not been covered by a change order

101
Q

disagreements between the contractor and owner over some aspect of contract performance

102
Q

construction documents that show in graphic and quantitative form the extent, design location, relationships, and dimensions of the work to be done

103
Q

a single volume that contains all written requirements for a building construction project

A

project manual

104
Q

constitute that portion of the written requirements for a building construction project that are contained in the divisions of a project manual

A

specifications

105
Q

presents a database that includes design data, drawings, specifications, materials and systems parameters, and life cycle data, for all the various disciplines involved in a project and relates those data to each other and to the project as a whole to present an overall view of the project

A

Building Information Modeling (BIM)

106
Q

a process whereby a prime design professional engaged by an owner, and the design professional’s consultants, prepare bidding documents and issue them to a group of constructors

107
Q

a process whereby an architect engaged by an owner, and the architect’s consultants, prepare negotiation documents

A

negotiation