Construction Technology & Environmental Services Flashcards

1
Q

With regards to West Quay Retail Park, what was the existing glazing to the front elevation?

A
  • Thermal boards and toughoned double glazed curtian walling certally with capped transoms and mullions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

With regards to Baker Street, how did you provide accurate budget costs?

A
  • BCIS/SPONS
  • Bank has internal costing system
  • Senior colleague
  • Case studies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

With regards to Abbey Wood, Kings Hill what was the current height of the raised access floor system, and why would it need to be altered?

A
  • Considering the property was a Cat B Fit-out as a data centre, the raised access floor system was 750mm (610mm - 1220mm).
  • The Feasiblity is for an office which tends to have a raised access floor system between 100mm and 250mm.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly