Construction Documents & Services 1 Flashcards

1
Q

mechanic’s lien

A

A claim on property by those who furnish material or labor for the construction of a building. Clear title to the property cannot be obtained until the claim is settled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

substantial completion

A

As defined in the AIA General Conditions, completion of a project to the point where the owner can occupy all or designated portions of the work for the purpose for which it is intended.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

overhead expense

A

Expenses indirectly incurred and not chargeable to a specific project. Also called indirect expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

subrogation

A

The substitution of one entity for another with regard to legal rights.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

record drawings

A

Drawings revised to show changes made during construction. Sometimes called as-built drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

contingency allowance

A

An amount included in a construction budget, normally 5-10%, to provide for unforeseen or unpredictable costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

consultant

A

An engineer or other specialist retained by the architect to provide specified professional services to the architect which the architect is required to provide to the owner under the owner-architect agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

sample

A

A material or assembly submitted for the architect’s approval prior to manufacture or delivery to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

contract documents

A

Working drawings, specifications, addenda, general conditions of the contract, supplementary conditions, and the owner-contractor agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

fast-track

A

Describing a construction procedure in which construction on each phase of a project is begun when it’s design is completed, without waiting for overall project design completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

warranty

A

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. Also called guarantee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Americans with Disabilities Act (ADA)

A

Federal civil rights legislation which establishes the right of persons with disabilities to equal access to sites and buildings and sets design guidelines for its implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

additional services (of the architect)

A

Professional services rendered by the architect, upon the owner’s request, in addition to the basic services identified in the owner architect agreement. Also called extra services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

means of egress

A

The elements which comprise an exit to the outside, including aisles, corridors, doors, and stairways.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

single prime contract

A

A contract for building construction under which one prime contractor is responsible for the entire project, in contrast to having separate contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

deposit for bidding documents

A

A deposit of money required for each bidder as security for the bidding documents, to ensure the return of the documents by unsuccessful bidders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

post-completion services

A

Additional services rendered to the owner by the architect following actual completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

superintendent

A

The contractor’s representative at the site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

guarantee

A

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. Also called warranty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

subcontractor

A

One who has a contract with a prime contractor to perform a portion of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

extra services

A

Professional services rendered by the architect, upon the owners request, in addition to the basic services identified in the owner-architect agreement. Also called additional services (of the architect).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

lowest acceptable bona fide bid

A

The lowest bid which complies with all the stipulated requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

advertisement for bids

A

Published public notice soliciting proposals for a construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

approved equal

A

A material or method that is approved by the architect as being equivalent to what was originally specified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Pert

A

Acronym for Project Evaluation Review Technique. A form of network analysis developed for military work and similar to the critical path method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Davis-Bacon Act

A

Federal legislation that requires the Department of Labor to set prevailing wages for government-financed construction projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

surety bond

A

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor). Also called a bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

indirect expense

A

Expenses indirectly incurred and not chargeable to a specific project. Also called overhead expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

basic services

A

The architectural services normally required for a building project, usually consisting of schematic design, design development, construction documents, bidding or negotiation, and construction contract administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

certificate of substantial completion

A

A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

observation

A

On-site examination of the contractor’s work by the architect to determine in general if it is proceeding in accordance with the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

supplementary conditions

A

Part of the contract documents, prepared by the architect, which may modify provisions of the general conditions of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

final completion

A

The completion of all work in accordance with the terms and conditions of the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

performance specification

A

A specification which defines products or systems by describing end results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

float

A

The extra time available for a construction activity above its estimated time duration, without causing any delay of project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

construction change directive

A

A document signed by the owner and the architect, which authorizes a change in the work, the contract sum, or the contract time. It is used when there is not complete agreement on the terms of a change order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

waiver of lien

A

A document by which one relinquishes the right of a mechanics lien against the property of another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

project budget

A

The sum established by the owner as available for the entire project, including the construction budget, land cost, equipment cost, financing cost, cost of professional services, and contingency allowances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

general contract

A

The agreement between the owner and the contractor for the construction of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

upset price

A

An amount established in an agreement between an owner and the contractor as the maximum cost of performing specified work. Also called the guaranteed maximum cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

special conditions

A

Part of the contract documents, other than the general and supplementary conditions, describing unique conditions of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

XCU

A

The exclusion from insurance coverage for liability arising out of (X) explosion or blasting, (C) collapse of or structural damage to a building, and (U) underground damage caused by mechanical equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

surety

A

An individual or company that guarantees to make good to another party the debt, default, or failure to perform of a third party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

substitution

A

A material, system, or product proposed by a contractor as being equivalent to that required by the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

cash allowance

A

An amount not included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in this manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

total quality management (TQM)

A

An approach to the delivery of goods or services in which quality is determined by customer satisfaction and conformance to requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

negligence

A

Failure to meet the ordinary standard of care expected of an architect or other professional in a specific circumstance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

clerk of the works

A

The owner’s job site representative.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

estimate

A

A forecast of probable costs, as opposed to a firm bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

construction management (CM)

A

Management services performed by the architect or others, over and above normal architectural services, that contribute to the control of time and cost in the construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

working drawings

A

The part of the contract documents, prepared by the architect, which graphically illustrates the construction required for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

payment request

A

A contractor’s written request for payment of the amount due on account of work completed and/or materials suitably stored on site. Also called application for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

change order

A

A written order to the contractor, prepared by the architect and signed by the owner, contractor, and architect, which authorizes a change in the work, the contract sum, or the contract time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

as-built drawings

A

Drawings revised to show changes made during construction. Also called record drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

prime contractor

A

Any contractor on a project who has a contract directly with the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

bid

A

A proposal by a contractor to do the work required by the contract documents for a stipulated sum of money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

progress payments

A

Payments made to the contractor during progress of the work on account of work completed and/or materials suitably stored.

58
Q

penalty

A

A charge against the contractor for failing to complete the project by a specific date.

59
Q

barrier-free provisions

A

Regulations which provide for accessibility to buildings and sites for persons with disabilities.

60
Q

sick building syndrome

A

A term used to describe poor air quality, which can lead to discomfort and possibly disease.

61
Q

separate prime contract

A

One of several owner-contractor agreements for a project, each of which provides for constructing a major portion of the work (general construction, electrical, mechanical, etc.) by a different contract.

62
Q

submittal

A

A shop drawing, project data, or sample submitted by the contractor to the architect for review prior to incorporation in the work.

63
Q

base bid

A

The sum of money stated in the bid for which the bidder offers to do the work, not including any alternate bids.

64
Q

punch list

A

A list of items to be corrected or completed, which is provided by the contractor and usually expanded by the architect based on a detailed inspection of the work prior to substantial completion.

65
Q

key plan

A

A small-scale plan of a building or complex of buildings.

66
Q

addenda

A

Statements or drawings which modify the basic contract documents after the latter have been issued to the bidders, but prior to taking of bids.

67
Q

shop drawings

A

Drawings prepared by the contractor, subcontractor, manufacturer, or supplier, showing how specific portions of the work shall be fabricated and/or installed.

68
Q

project manual

A

The manual prepared by the architect for a project, including the technical specifications, bidding instructions and forms, general conditions, supplementary conditions, special conditions, and other legal and administrative documents.

69
Q

construction documents

A

Working drawings and specifications.

70
Q

contract sum

A

The total amount payable by the owner to the contractor, as stated in the owner-contractor agreement, for performing the work under the contract documents.

71
Q

statute of limitations

A

An ordinance which specifies the period of time within which legal action must be brought to obtain legal relief for damage or injury.

72
Q

deductive alternate

A

A proposal by a bidder for an amount to be subtracted from the base bid if the corresponding change in the work is accepted.

73
Q

retainage

A

An amount withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement.

74
Q

closed proprietary specification

A

A proprietary specification which requires a particular brand or trade name and does not permit any substitution.

75
Q

standard of care

A

The requirement that a professional exercise reasonable ability and judgement in a specific circumstance, the absence of which constitutes negligence. Also called due care.

76
Q

hold harmless clause

A

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. Also called indemnification.

77
Q

comprehensive services

A

The architect’s basic services expanded to include certain additional services, such as programming, land use studies, and so on.

78
Q

work

A

All materials and/or labor required for a project.

79
Q

construction budget

A

The sum established by the owner as available for construction of the project.

80
Q

NIC

A

Abbreviation for not-in-contract, referring to items neither furnished nor installed by the contractor.

81
Q

specifications

A

Part of the contract documents, comprising written descriptions of materials, construction systems, and workmanship.

82
Q

express warranty

A

A legally enforceable promise made by the warrantor.

83
Q

project representative

A

The architect’s representative at the site, who assists in the general administration of the construction contract for a project.

84
Q

certificate for payment

A

A statement by the architect informing the owner of the amount due the contractor on account of work completed and/or materials suitably stored.

85
Q

application for payment

A

A contractor’s written request for payment of the amount due on account of work completed and/or materials suitably stored on site. Also called payment request.

86
Q

alternate bid

A

A proposal by a bidder for an amount to be subtracted from or added to the base bid if the corresponding change in the work is accepted. This may be either a deductive or additive alternate.

87
Q

agent

A

One who acts on behalf of another.

88
Q

certificate of occupancy

A

A document issued by the governing authority stating that a building complies with applicable laws and permitting occupancy for its designated use.

89
Q

Division One

A

The General Requirements Division of the specifications which establishes the administrative and procedural duties of the contractor, architect, and owner during construction.

90
Q

proprietary specification

A

A specification which calls for desired materials, products, systems, and equipment by their trade names and model numbers.

91
Q

critical path method (CPM)

A

A system of planning and scheduling construction operations which analyzes sequences and durations of time using network diagrams.

92
Q

direct expense

A

Expense items directly incurred by or attributable to a specific project.

93
Q

contract time

A

The period of time within which the work must be completed, as established in the contract documents.

94
Q

general conditions

A

The part of the contract documents which states the rights, responsibilities, and relationships of the parties involved, usually by means of standard documents published by the A.I.A.

95
Q

insurance

A

Coverage by contract (insurance policy), whereby one party (the insurance company) agrees to indemnify or reimburse another (the insured) against loss from a specified hazard.

96
Q

arbitration

A

An alternative to litigating a dispute, in which one or more arbitrators hears the evidence and renders a decision.

97
Q

indemnification

A

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. Also called the hold harmless clause.

98
Q

bonus and penalty clause

A

A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date, and for a charge (penalty) against the contractor for failing to complete the project by that date.

99
Q

additive alternate

A

A proposal by a bidder for an amount to be added to the base bid if the corresponding change in the work is accepted.

100
Q

addition (to the contract sum)

A

An amount added to the contract sum either by an accepted additive alternate or by a change order.

101
Q

supervision

A

Direction of the work by the contractor’s personnel. Supervision is not the responsibility of the architect.

102
Q

trade discount

A

The difference between the list price and the actual price paid.

103
Q

date of substantial completion

A

The date, certified by the architect, when the construction is sufficiently completed, in accordance with the contract documents, so that the owner can occupy the project for the intended use.

104
Q

reference specification

A

A specification which refers to quality standards established by recognized testing authorities or by the federal government.

105
Q

due care

A

The requirement that a professional exercise reasonable ability and judgement in a specific circumstance, the absence of which constitutes negligence. Also called standard of care.

106
Q

program

A

A written statement of the owner’s conditions and requirements for the project.

107
Q

open proprietary specification

A

A proprietary specification which names several acceptable materials, products, or systems, any of which may be used by the contractor.

108
Q

extra

A

An item of work involving additional cost.

109
Q

unit price

A

An amount, stated in dollars per unit, provided by the contractor with his bid for adding or deleting specific portions of the work.

110
Q

descriptive specification

A

A specification which describes all product components, arrangements, assembly methods, properties, and other details and requirements.

111
Q

release of lien

A

A legal document signed by a supplier of material or labor for a project, which releases his mechanic’s lien against the property.

112
Q

notice to bidders

A

Instructions in the bidding documents for preparing and submitting bids for a project. Also called instructions to bidders.

113
Q

bond

A

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor). Also called surety bond.

114
Q

performance bond

A

A bond which guarantees to the owner that the contractor will perform the work in accordance with the contract documents.

115
Q

invitation to bid

A

An invitation to a selected list of contractor’s soliciting bids for a project.

116
Q

bid bond

A

A surety bond guaranteeing that the bidder will sign a contract, if offered, in accordance with his or her proposal.

117
Q

instructions to bidders

A

Instructions in the bidding documents for preparing and submitting bids for a project. Also called notice to bidders.

118
Q

incentive clause

A

A clause in a cost plus fee contract between the owner and contractor in which the savings between the guaranteed maximum cost and the actual project costs are proportionally shared.

119
Q

cost-plus-fee contract

A

An agreement under which the contractor, or the architect, is reimbursed for his or her costs, and, in addition, is paid a fee for his services.

120
Q

stipulated sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also known as a lump sum contract.

121
Q

lump sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also called a stipulated sum contract.

122
Q

percentage agreement

A

An owner-architect agreement under which the professional fee is based upon a percentage of the construction cost of the project.

123
Q

multiple of direct personnel expense agreement

A

An agreement providing for payment for professional services based upon the direct personnel expense multiplied by an agreed factor.

124
Q

professional liability insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called errors and omissions insurance.

125
Q

certificate of insurance

A

A memorandum which outlines the types and limits of the insurance coverages carried by the contractor for a project.

126
Q

fixed limit of construction cost

A

The maximum allowable cost of the construction work, as established in the owner-architect agreement.

127
Q

guaranteed maximum cost

A

An amount established in an agreement between an owner and a contractor as the maximum cost of performing specified work. Also called the upset price.

128
Q

property insurance

A

Fire and property damage insurance for a project during construction, usually purchased by the owner. Also called builder’s risk insurance.

129
Q

bidding documents

A

The invitation to bid, instructions to bidders, bid form, and the contract documents.

130
Q

letter of intent

A

A letter signifying intention to enter into a formal agreement and setting forth the general terms thereof.

131
Q

option

A

A choice given to the contractor to provide specified alternates without prior approval of the architect.

132
Q

schedule of values

A

A statement furnished to the architect by the contractor reflecting the amounts to be slotted for the principal divisions of the work. It serves as a guide for reviewing the contractor’s periodic application for payment.

133
Q

CSI Master Format

A

A systematic listing of construction trades, materials, systems, and administrative requirements published by the Construction Specifications Institute (CSI) for the purpose of organizing construction specifications.

134
Q

liquidated damages

A

A sum chargeable against the contractor as reimbursement for damages suffered by the owner because of the contractor’s failure to complete the work within a specified time.

135
Q

labor and material payment bond

A

A bond guaranteeing to the owner that the contractor will pay for all labor and materials used for the project.

136
Q

workers’ compensation insurance

A

Insurance which covers workers’ job-related injuries, usually required by law.

137
Q

builder’s risk insurance

A

Fire and property damage insurance for a project during construction, usually purchased by the owner. Also called property insurance.

138
Q

direct personnel expense (DPE)

A

Salaries and wages attributable to a specific project, plus benefits such as employment taxes, insurance, sick leave, holidays, vacations, pensions, and similar contributions and benefits.

139
Q

completion bond

A

A bond obtained by the contractor or owner, which guarantees that the project will be completed free of liens.

140
Q

errors and omissions insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called professional liability insurance.

141
Q

liability insurance

A

Insurance which financially protects the insured against liability on account of bodily injury or property damage sustained by another.