Who is a Commercial Client?
A commercial client is anyone (individual, partnership or organisation) who has construction work carried out for them that is done in connection with a business, whether the business operates for profit or not.
Who is a Domestic Client?
A domestic client is anyone who has construction work carried out for them that is not done in connection with a business.
Who is the Principle Contractor?
A principal contractor is the contractor with control over the construction phase of a project involving more than one contractor. They are appointed in writing by the client to plan, manage, monitor and coordinate health and safety during this phase.
Who is the Principle Designer?
A principal designer can be an organisation or individual who is appointed by the client to take the lead in planning, managing, monitoring and coordinating health and safety during the pre-construction phase (design and planning stage) of a project involving, or likely to involve, more than one contractor.
Who is the Contractor?
A contractor is an organisation or individual who directly employs or engages construction workers or as part of their business carries out, manages or controls construction work. Contractors include sub-contractors, any individual, sole trader or self-employed worker.
Which one of the following is true about the Principle Designer?
a. Approves the appointment of Designers
b. Approves the appointment of Contractors
c. Approves the appointment of Subcontractors
d. Approves the alteration of Designs
e. None of the above
E
Which of the following Construction Statutory Instrument is considered the most comprehensive after the HSAW ETC 1974?
a. COSHH
b. 2015 CDM
c. WAH
d. LOLER
B
Under 2015 CDM, who is responsible for developing a Construction Phase Plan? a. Designer
b. The Client
c. The Principal Contractor
d. The Principal Designer
C
Under 2015 CDM which of the following duty holders is the client expected to appoint first?
a. Principal Contractor
b. Designer
c. Principal Designer
d. Sub Contractor
B
Under 2015CDM who is defined as a designer
a. Architect
b. Quantity Surveyor
c. Architectural Technologist
d. Chartered Surveyor
e. Any of the above
E
With regard to 2015 CDM, which one of the following statements is true?
a. The principal Designer advises clients on the appointment of a Principal Contractor
b. The Designer should not accept being appointed until they are sure the clients understands their responsibilities under CDM
c. A principal contractor should not accept being appointed until they are sure the clients understands their responsibilities under CDM
d. All of the above
D
With regard to 2015CDM, which one of the following is true about the appointment of a Designer?
a. When there are more than one contractor, it is the Principal designer’s duty to remind the client of their duties under CDM
b. The Client should seek approval of Principal Designer before appointing a Designer
c. The designer can not start the design work until approved by Principal Designer
d. When there are more than one contractor, it is the designer duty to remind the client of their duties under CDM
A
At the preconstruction phase which duty holder has responsibility for planning, monitoring and coordinating matters relating to health and safety?
a. The Designer
b. The Principal Contractor
c. The Principal Designer
d. The client
C
Under the 2015 CDM, which hierarchy of liability will have been complied with which compels the client to appoint well resourced competent duty holders?
a. Absolute liability
b. Practicable liability
c. Reasonably practicable liability
d)All of the above
A
Which One of the following individuals is responsible for providing other duty holders with preconstruction information?
a. The Designer
b. The Principal Contractor
c. The Principal Designer
d. The client
C